Attendees: Elton S., Ravi A., Dave D. David L., Paul B., Ben W., Ed B. ES: Collaboration meeting report. MOU's - JLab MOU needs to have a lot of care to be as accurate as reasonably possible. EB: Calorimeter can be made 2/month which means 2 years for fabrication. Not really room to store them all though. PB: More motivation for hall construction. ES: Building not expected to be ready until the end of 2007. EB: The 2 year schedule is based on completely smooth operation for 2 years. 3 years are more realistic. Prototype to be constructed this summer and then tested at Serpukov. 2005 is earliest to expect real production on BCAL. ES: I'll circulate schedules for people to review. DD: What was the decision on how central detectors will be inserted (one end or both ends)? Answer- both ends. PB: Two magnet tagger got little resistance at meeting. ES: Some concerns were raised in smaller meeting. Concerns about the vacuum box. How to support it between two magnets. PB: That's easy. DD: What is expected (construction) completion date? ES: Not well know. Based on optimistic estimates, 2008. DD: May be hard to get all funding in just a 3 year period. EB: May be lucky to get CD1 a year from now. Construction can't start until 2006. ES: CD1 doesn't give money for construction so construction can't occur in 2006 (unless SURA loans the money up front.) PB: Any commitment to taking over Cherenkov design. ES: Collaborators from UTenn have expressed serious interest. EB: We have post-doc who can start working on simulations. He has some experience with PID. --- More discussion on tagger magnet --- PB: Schedule for (solenoid) magnet: Jan 2006 start moving components into test area at JLab. Ends Dec. 2007 EB: Schedule seems really long. (First BCAL module can't be installed until jan 2008.) ES: Looks like we need space at JLab in Aug. 2005 according to this schedule. --- More discussion on details of solenoid schedule --- EB: At very least 9 months will be needed for BCAL (w/ electronics) installation. ES: JLab MOU - We need to review the personel listed and the fraction of FTE time. Can be obtained from Curtis's website. --- Discussion of manpower. DAQ group should maybe come up with a list of milestones in CODA development.--- ES: Need to finalize who will be responsible for FADC project. ES: What do we do next week? 10:17 adjorn