Difference between revisions of "One Week Pause in Running"
From Hall D Ops Wiki
(→One Week Pause in Running) |
(→One Week Pause in Running) |
||
Line 2: | Line 2: | ||
* Goal: Reinstall tagger detectors/electronics and check data. | * Goal: Reinstall tagger detectors/electronics and check data. | ||
* Expected Schedule: | * Expected Schedule: | ||
− | ** Oct | + | ** Oct 28 - Nov 02 : 6 days, depends on the accelerator program to be carried out meanwhile |
* Responsibility: Hall D | * Responsibility: Hall D | ||
* Priority: High | * Priority: High |
Revision as of 14:45, 18 September 2014
One Week Pause in Running
- Goal: Reinstall tagger detectors/electronics and check data.
- Expected Schedule:
- Oct 28 - Nov 02 : 6 days, depends on the accelerator program to be carried out meanwhile
- Responsibility: Hall D
- Priority: High
- Conditions:
- No beam, Tagger hall and Hall D are open.
- Acivities
- Reinstall the tagger "microscope" (TAGM) and the electronics, reconnect the cables.
- Analyze the data taken so far and identify possible problems.
- Use this downtime to fix the identified hardware issues.
- Using reconstructed tracks find the location of the beam spot