Difference between revisions of "One Week Pause in Running"
From Hall D Ops Wiki
(→One Week Pause in Running) |
(→One Week Pause in Running) |
||
Line 10: | Line 10: | ||
* Acivities | * Acivities | ||
# Reinstall the tagger "microscope" (TAGM) and the electronics, reconnect the cables. | # Reinstall the tagger "microscope" (TAGM) and the electronics, reconnect the cables. | ||
+ | # Remove upstream collimator. | ||
# Analyze the data taken so far and identify possible problems. | # Analyze the data taken so far and identify possible problems. | ||
# Use this downtime to fix the identified hardware issues. | # Use this downtime to fix the identified hardware issues. |
Revision as of 17:19, 1 October 2014
One Week Pause in Running
- Goal: Reinstall tagger detectors/electronics and check data.
- Expected Schedule:
- Oct 28 - Nov 02 : 6 days, depends on the accelerator program to be carried out meanwhile
- Responsibility: Hall D
- Priority: High
- Conditions:
- No beam, Tagger hall and Hall D are open.
- Acivities
- Reinstall the tagger "microscope" (TAGM) and the electronics, reconnect the cables.
- Remove upstream collimator.
- Analyze the data taken so far and identify possible problems.
- Use this downtime to fix the identified hardware issues.
- Using reconstructed tracks find the location of the beam spot