Operation
Procedures: signed documents
Operational Safety Procedure (OSP)
- Hall D Solenoid Magnet - Cryogenic Operations: ENG-12-19709-OSP
- Hall D Solenoid Power Supply Test and Maintenance: -13-21781-OSP
- Hall D Solenoid Powered Operations OSP: FEL-13-22021-OSP
Procedure and Checklist
- Solenoid Cooldown Checklists
- D000000402-P003 Rev A
- Solenoid Vacuum System Controls Check Procedure
- D000000402P004
- Hall D Solenoid System Hi-Pot Procedure
- D000000402P006 RevA
- Solenoid Voltage Tap Check List
- D000000402-P010
- Hall D Solenoid Pre Power-Up Checklists
- D000000402P007
- Hall D Solenoid Magnet Power Supply Maintenance Turn-on Checklist
- D000001611P000 Rev A
- Hall D Solenoid Magnet Power Supply Internal Interlock Checklist
- D000001611P001 Rev B
- Ground Fault Detector Rheostat Setting Procedure
- D000000402P011
- Hall D Solenoid System Hi-Pot Procedure
- D000000402P006 RevA
- Solenoid Quench Detector Tuning Procedure
- D000000402P005
- Hall-D Solenoid Commissioning Procedure
- D000000402P002
Technical References
Magnet
Power Supply
Cryogenics System
Programmable Logic Control (PLC)
PXI Fast DAQ System
Quench Detector
Ground Fault Detector
Old Wiki Page