One Week Pause in Running
From Hall D Ops Wiki
One Week Pause in Running
- Goal: Reinstall tagger detectors/electronics and check data.
- Expected Schedule:
- Oct 8 - Oct 13 : 6 days, depends on the accelerator program to be carried out meanwhile
- Responsibility: Hall D
- Priority: High
- Conditions:
- No beam, Tagger hall and Hall D are open.
- Acivities
- Reinstall the tagger "microscope" (TAGM) and the electronics, reconnect the cables.
- Analyze the data taken so far and identify possible problems.
- Use this downtime to fix the identified hardware issues.
- Using reconstructed tracks find the location of the beam spot