Difference between revisions of "Drift Chamber Alignment"

From Hall D Ops Wiki
Jump to: navigation, search
(Drift Chamber Alignment)
 
Line 2: Line 2:
 
# Goal: Collect data with no or low field.
 
# Goal: Collect data with no or low field.
 
# Responsibility: HallD
 
# Responsibility: HallD
* Expected Schedule:  
+
* Expected Schedule: See start dates in the run coordination meeting pages [https://halldweb1.jlab.org/wiki/index.php/Run_Coordination_Meetings#Meeting_General_Agenda here] and the general schedule [https://hdops.jlab.org/wiki/index.php/Fall_2014_Commissioning_Plan#Run_Plan here]: Duration of the Drift Chamber Alignment : 4 days
** Nov 6 - Nov 9 : 4 days
+
 
# Conditions:
 
# Conditions:
 
#* Tagger hall equipment in place and operating.  
 
#* Tagger hall equipment in place and operating.  

Latest revision as of 10:18, 20 October 2014

Drift Chamber Alignment

  1. Goal: Collect data with no or low field.
  2. Responsibility: HallD
  • Expected Schedule: See start dates in the run coordination meeting pages here and the general schedule here: Duration of the Drift Chamber Alignment : 4 days
  1. Conditions:
    • Tagger hall equipment in place and operating.
    • Beam 50nA CW
    • Radiator is 0.2 - 1.0 10-4 RL, depending on the FDC and trigger rates.
    • Collimator hole is 5 mm.
    • Solenoid 0-300A depending on backgrounds.
    • GlueX detectors are on.
    • Thin commissioning targets at various positions.
  2. Activities
    • If time permits, collect data with target in several positions.

Back to main Fall14 commissioning page