Difference between revisions of "Fall 2014 Commissioning Plan"

From Hall D Ops Wiki
Jump to: navigation, search
(Created page with "__TOC__ ==Tune Electron Beam== # Goal: Get electron beam to the dump in the tagger hall. # Responsibility: Accelerator, HallD, RadCon. # Conditions: #* Tagger hall equipment r...")
 
(Tune Electron Beam)
Line 12: Line 12:
 
#* Check radiation levels in the tagger hall.
 
#* Check radiation levels in the tagger hall.
 
#* Check for photons and radiation levels in the collimator cave.
 
#* Check for photons and radiation levels in the collimator cave.
 +
==Tune Photon Beam==
 +
# Goal: Tune the photon beam to go through the collimator, the experimental target area, and into the photon beam dump.
 +
# Responsibility: HallD, Accelerator, RadCon.
 +
# Conditions:

Revision as of 08:12, 2 July 2014

Tune Electron Beam

  1. Goal: Get electron beam to the dump in the tagger hall.
  2. Responsibility: Accelerator, HallD, RadCon.
  3. Conditions:
    • Tagger hall equipment removed or shielded. This includes the microscope (TAGM) and the electronics.
    • Pulsed beam may be used.
    • No radiator installed.
    • Collimator blocks the photon beamline to Hall D.
  4. Activities:
    • Tune beam to the dump, check the beam specification.
    • Check radiation levels in the tagger hall.
    • Check for photons and radiation levels in the collimator cave.

Tune Photon Beam

  1. Goal: Tune the photon beam to go through the collimator, the experimental target area, and into the photon beam dump.
  2. Responsibility: HallD, Accelerator, RadCon.
  3. Conditions: