Difference between revisions of "Fall 2014 Commissioning Plan"

From Hall D Ops Wiki
Jump to: navigation, search
(Tune Photon Beam)
Line 16: Line 16:
 
# Responsibility: HallD, Accelerator, RadCon.
 
# Responsibility: HallD, Accelerator, RadCon.
 
# Conditions:
 
# Conditions:
#*
+
#* Tagger hall equipment removed or shielded. This includes the microscope (TAGM) and the electronics.
 +
#* Beam 50nA CW (if possible).
 +
#* Radiator 10<sup>-4</sup> RL.
 +
#* Collimator hole is 3.5mm at nominal beam position.
 +
#* Solenoid on with current ~1000A.
 +
#* GlueX detectors off (except peripheral such as BCAL)
 +
#* No target in place (use air along beamline as target).
 +
# Activities

Revision as of 08:16, 2 July 2014

Tune Electron Beam

  1. Goal: Get electron beam to the dump in the tagger hall.
  2. Responsibility: Accelerator, HallD, RadCon.
  3. Conditions:
    • Tagger hall equipment removed or shielded. This includes the microscope (TAGM) and the electronics.
    • Pulsed beam may be used.
    • No radiator installed.
    • Collimator blocks the photon beamline to Hall D.
  4. Activities:
    • Tune beam to the dump, check the beam specification.
    • Check radiation levels in the tagger hall.
    • Check for photons and radiation levels in the collimator cave.

Tune Photon Beam

  1. Goal: Tune the photon beam to go through the collimator, the experimental target area, and into the photon beam dump.
  2. Responsibility: HallD, Accelerator, RadCon.
  3. Conditions:
    • Tagger hall equipment removed or shielded. This includes the microscope (TAGM) and the electronics.
    • Beam 50nA CW (if possible).
    • Radiator 10-4 RL.
    • Collimator hole is 3.5mm at nominal beam position.
    • Solenoid on with current ~1000A.
    • GlueX detectors off (except peripheral such as BCAL)
    • No target in place (use air along beamline as target).
  4. Activities