Fall 2014 Commissioning Plan

From Hall D Ops Wiki
Revision as of 08:38, 2 July 2014 by Cmeyer (Talk | contribs) (Collect Beam Data for Detector Checkout)

Jump to: navigation, search

Tune Electron Beam

  1. Goal: Get electron beam to the dump in the tagger hall.
  2. Responsibility: Accelerator, HallD, RadCon.
  3. Conditions:
    • Tagger hall equipment removed or shielded. This includes the microscope (TAGM) and the electronics.
    • Pulsed beam may be used.
    • No radiator installed.
    • Collimator blocks the photon beamline to Hall D.
  4. Activities:
    • Tune beam to the dump, check the beam specification.
    • Check radiation levels in the tagger hall.
    • Check for photons and radiation levels in the collimator cave.

Tune Photon Beam

  1. Goal: Tune the photon beam to go through the collimator, the experimental target area, and into the photon beam dump.
  2. Responsibility: HallD, Accelerator, RadCon.
  3. Conditions:
    • Tagger hall equipment removed or shielded. This includes the microscope (TAGM) and the electronics.
    • Beam 50nA CW (if possible).
    • Radiator 10-4 RL.
    • Collimator hole is 3.5mm at nominal beam position.
    • Solenoid on with current ~1000A.
    • GlueX detectors off (except peripheral such as BCAL)
    • No target in place (use air along beamline as target).
  4. Activities
    • Use the beam profiler to move the photon beam to the hole in the collimator. (Accel, Hall D)
    • Check radiation levels in the collimator cave and HallD. (RadCon)
    • Turn the PS magnet on and install a 10-3 converter. Tune the PS coarse detectors (Hall D).
    • Use the PS coarse detectors to verify the beam location.
    • Insert a convertor in the PS and leave running with its own trigger throughout the run period.
    • Calibrate the active collimator by scanning (desirable activity). (HallD and Accelerator)
    • Use other detectors (under discussion) to verify the beam position with respect to the beam pipes and the target (if time permits) (Hall D)
    • Turn detectors on slowly, moving in from the peripheral to the center. Monitor the rates and background levels. (Hall D)
    • Insert a thin target at the nominal target position. Set the regular trigger and take data for about 1 shift.

One Week Pause in Running

  1. Goal: Reinstall tagger detectors and check data.
  2. Responsibility: HallD
  3. Conditions:
    • Beam off in the Hall.
  4. Acivities
    • Reinstall the tagger detectors, TAGM and TAGH.
    • Check validity of data offline. Use as feedback to detector settings.
    • Check/modify the online monitoring histograms based on data.

Collect Beam Data for Detector Checkout

  1. Goal: Collect 5 days of beam data.
  2. Responsibility: HallD
  3. Conditions:
    • Tagger hall equipment in place and operating.
    • Beam 50nA CW
    • Radiator is 10-4.
    • Collimator hole is 3.5mm.
    • Solenoid on at 1200A
    • GlueX detectors are on.
    • Thin commissioning target at nominal position.
  4. Activities
    • Verify photon beam position and background levels.
    • Take data with the regular trigger for five days

Optimize Detector Settings

  1. Goal: Verify optimal settings for detectors.
  2. Responsibility: HallD
  3. Conditions:
    • Tagger hall equipment in place and operating.
    • Beam 50nA CW
    • Radiator is 10-4.
    • Collimator hole is 3.5mm.
    • Solenoid on at 1200A
    • GlueX detectors are on.
    • Thin commissioning target at nominal position.
  4. Activities
    • If time permits, dedicated running to optimize settings of detectors will be carried out.

Drift Chamber Alignment

  1. Goal: Collect data with no or low field.
  2. Responsibility: HallD
  3. Conditions:
    • Tagger hall equipment in place and operating.
    • Beam 50nA CW
    • Radiator is 10-4.
    • Collimator hole is 3.5mm.
    • Solenoid 0-300A depending on backgrounds.
    • GlueX detectors are on.
    • Thin commissioning target at various positions.
  4. Activities
    • If time permits, collect data with target in several positions.