Fall 2014 Commissioning Plan

From Hall D Ops Wiki
Revision as of 19:29, 8 August 2014 by Gen (Talk | contribs)

Jump to: navigation, search

General Information

  • Goals
    1. Clean tune of the electron beam into the Tagger Dump
    2. Commissioning of the unpolarized photon beam
    3. Commissioning of the Hall D equipment under "soft" conditions:
      • low-intensity unpolarized photon beam <10 MHz/GeV at the endpoint
      • thin solid targets instead of the regular liquid hydrogen target
      • solenoid current 1200 A instead of the nominal 1300 A
  • Schedule and Hall Availability: The accelerator run is scheduled for 19-Sep-14 - 22-Dec-14. 3 week are assigned for Hall D commissioning with photon beam (see [1]). The tentative plan is:
    1. Accelerator: beam recovery and 5.5 pass beam tune to the dumplette Sep 19-29. Hall D/Tagger are open.
    2. Accelerator: electron beam tune to the Tagger Dump, 29-Sep-14 - 03-Oct-14. Hall D/Tagger are locked. TAGM and the electronics are removed from the Tagger Hall.
    3. Accelerator/Hall D: Photon beam tune to Hall D and the initial equipment checkout, Oct 4-5. Halls are locked.
    4. Hall D: Re-installation of the Tagger equipment (TAGM and the electronics), Oct 6-11. Halls are open.
    5. Hall D: Equipment commissioning with photon beam, Oct 12-31. Halls are locked.
  • Expected Staffing:
    • Run Coordinator: Alexandre Deur
    • Online Shifts: 3 persons per shift, one with solenoid training.
    • Offline Shifts: at least two people looking at data written to tape.
  • Coordination Activities:
  • Activity Priority
    • High: Activity should be completed, contingencies in place for issues.
    • Medium: Desirable to complete the activity.
    • Low: Activity would be useful if time permits us to do it.
  • Activities planned for the next run in Spring 2015:
    • Installation of liquid hydrogen target.
    • Installation of diamond radiator in goniometer.
    • Running at 1300A solenoid current.