* Acivities
 
* Acivities
 
# Reinstall the tagger "microscope" (TAGM) and the electronics, reconnect the cables.
 
# Reinstall the tagger "microscope" (TAGM) and the electronics, reconnect the cables.
 +
# Remove upstream collimator.
 
# Analyze the data taken so far and identify possible problems.
 
# Analyze the data taken so far and identify possible problems.
 
# Use this downtime to fix the identified hardware issues.
 
# Use this downtime to fix the identified hardware issues.

Revision as of 17:19, 1 October 2014

One Week Pause in Running

  • Goal: Reinstall tagger detectors/electronics and check data.
  • Expected Schedule:
    • Oct 28 - Nov 02 : 6 days, depends on the accelerator program to be carried out meanwhile
  • Responsibility: Hall D
  • Priority: High
  • Conditions:
  1. No beam, Tagger hall and Hall D are open.
  • Acivities
  1. Reinstall the tagger "microscope" (TAGM) and the electronics, reconnect the cables.
  2. Remove upstream collimator.
  3. Analyze the data taken so far and identify possible problems.
  4. Use this downtime to fix the identified hardware issues.
  5. Using reconstructed tracks find the location of the beam spot

Back to main Fall14 commissioning page