==One Week Pause in Running==
 
==One Week Pause in Running==
 
* Goal: Reinstall tagger detectors/electronics and check data.
 
* Goal: Reinstall tagger detectors/electronics and check data.
* Schedule: Start Oct 8, duration 6 days depends on the accelerator program to be carried out meanwhile
+
* Expected Schedule:
 +
** Oct 8 - Oct 13 : 6 days, depends on the accelerator program to be carried out meanwhile  
 
* Responsibility: Hall D
 
* Responsibility: Hall D
 
* Priority: High
 
* Priority: High

Revision as of 19:03, 22 August 2014

One Week Pause in Running

  • Goal: Reinstall tagger detectors/electronics and check data.
  • Expected Schedule:
    • Oct 8 - Oct 13 : 6 days, depends on the accelerator program to be carried out meanwhile
  • Responsibility: Hall D
  • Priority: High
  • Conditions:
  1. No beam, Tagger hall and Hall D are open.
  • Acivities
  1. Reinstall the tagger "microscope" (TAGM) and the electronics, reconnect the cables.
  2. Analyze the data taken so far and identify possible problems.
  3. Use this downtime to fix the identified hardware issues.
  4. Using reconstructed tracks find the location of the beam spot