One Week Pause in Running

From Hall D Ops Wiki
Revision as of 17:19, 1 October 2014 by Deurpam (Talk | contribs) (One Week Pause in Running)

Jump to: navigation, search

One Week Pause in Running

  • Goal: Reinstall tagger detectors/electronics and check data.
  • Expected Schedule:
    • Oct 28 - Nov 02 : 6 days, depends on the accelerator program to be carried out meanwhile
  • Responsibility: Hall D
  • Priority: High
  • Conditions:
  1. No beam, Tagger hall and Hall D are open.
  • Acivities
  1. Reinstall the tagger "microscope" (TAGM) and the electronics, reconnect the cables.
  2. Remove upstream collimator.
  3. Analyze the data taken so far and identify possible problems.
  4. Use this downtime to fix the identified hardware issues.
  5. Using reconstructed tracks find the location of the beam spot

Back to main Fall14 commissioning page