  1. Goal: Reinstall tagger detectors/electronics and check data.
  2. Responsibility: HallD
  3. Priority: High
  4. Conditions:
    • Beam off in the Hall.
  5. Acivities
    • Reinstall the tagger detector, TAGM and the electronics, reconnect the cables.
    • Check validity of data offline. Use as feedback to detector settings.
    • Check/modify the online monitoring histograms based on data.