One Week Pause in Running

From Hall D Ops Wiki
Revision as of 11:29, 7 August 2014 by Gen (Talk | contribs) (One Week Pause in Running)

Jump to: navigation, search

Main Page

Tune Electron Beam

Tune Photon Beam

One Week Pause in Running

  • Goal: Reinstall tagger detectors/electronics and check data.
  • Responsibility: Hall D
  • Priority: High
  • Conditions:
  1. Beam off in the Hall.
  • Acivities
  1. Reinstall the tagger detector, TAGM and the electronics, reconnect the cables.
  2. Check validity of the data taken so far. Use as feedback to detector settings.
  3. Check/modify the online monitoring histograms based on data.
  4. Using reconstructed tracks find the location of the beam spot

Collect Beam Data for Detector Checkout

Optimize Detector Settings

Drift Chamber Alignment

Collect More Regular Data