One Week Pause in Running

  • Goal: Reinstall tagger detectors/electronics and check data.
  • Schedule: Start Oct 9, duration 6-7 days depends on the accelerator program to be carried out meanwhile
  • Responsibility: Hall D
  • Priority: High
  • Conditions:
  1. No beam, Tagger hall and Hall D are open.
  • Acivities
  1. Reinstall the tagger "microscope" (TAGM) and the electronics, reconnect the cables.
  2. Analyze the data taken so far and identify possible problems.
  3. Use the down time to fix the identified hardware issues.
  4. Using reconstructed tracks find the location of the beam spot

Collect Beam Data for Detector Checkout

Optimize Detector Settings

Drift Chamber Alignment

Collect More Regular Data