One Week Pause in Running

From Hall D Ops Wiki
Revision as of 10:11, 21 August 2014 by Deurpam (Talk | contribs)

Jump to: navigation, search

One Week Pause in Running

  • Goal: Reinstall tagger detectors/electronics and check data.
  • Schedule: Start Oct 8, duration 6 days depends on the accelerator program to be carried out meanwhile
  • Responsibility: Hall D
  • Priority: High
  • Conditions:
  1. No beam, Tagger hall and Hall D are open.
  • Acivities
  1. Reinstall the tagger "microscope" (TAGM) and the electronics, reconnect the cables.
  2. Analyze the data taken so far and identify possible problems.
  3. Use this downtime to fix the identified hardware issues.
  4. Using reconstructed tracks find the location of the beam spot