(Operational Safety Procedure (OSP))
(Procedure and Checklist)
Line 11: Line 11:
 
=== Procedure and Checklist ===
 
=== Procedure and Checklist ===
  
 +
;Solenoid Cooldown Checklists: [https://misportal.jlab.org/jlabDocs/document.seam?id=81510&cid=16269 D000000402-P003 Rev A]
 +
 +
;Solenoid Vacuum System Controls Check Procedure: [https://misportal.jlab.org/jlabDocs/document.seam?id=81089  D000000402P004]
 +
 +
;Hall D Solenoid System Hi-Pot Procedure: [https://misportal.jlab.org/jlabDocs/document.seam?id=81384 D000000402P006 RevA]
 +
 +
;Solenoid Voltage Tap Check List: [https://misportal.jlab.org/jlabDocs/document.seam?id=81703  D000000402-P010]
 +
 +
;Hall D Solenoid Pre Power-Up Checklists: [https://misportal.jlab.org/jlabDocs/document.seam?id=81652 D000000402P007]
 +
 +
;Hall D Solenoid Magnet Power Supply Maintenance Turn-on Checklist: [https://misportal.jlab.org/jlabDocs/document.seam?id=73852 D000001611P000 Rev A]
 +
 +
;Hall D Solenoid Magnet Power Supply Internal Interlock Checklist: [https://misportal.jlab.org/jlabDocs/document.seam?id=73853 D000001611P001 Rev B]
 +
 +
; Ground Fault Detector Rheostat Setting Procedure: [https://misportal.jlab.org/jlabDocs/document.seam?id=81635 D000000402P011]
 +
 +
;Hall D Solenoid System Hi-Pot Procedure: [https://misportal.jlab.org/jlabDocs/document.seam?id=81384 D000000402P006 RevA]
 +
 +
;Solenoid Quench Detector Tuning Procedure: []
 
* '''Magnet Turn-ON Procedure''' [M:\halld_engineering\Solenoid\Improvements after Aug'13 Test\140617Solenoid turn on trackingTracking.xlsx]
 
* '''Magnet Turn-ON Procedure''' [M:\halld_engineering\Solenoid\Improvements after Aug'13 Test\140617Solenoid turn on trackingTracking.xlsx]
 
* '''Hall D Solenoid Pre Power-Up Checklists''' [https://misportal.jlab.org/jlabDocs/version.seam?docVersionId=85448&cid=22680 Link to Doc Control]
 
* '''Hall D Solenoid Pre Power-Up Checklists''' [https://misportal.jlab.org/jlabDocs/version.seam?docVersionId=85448&cid=22680 Link to Doc Control]

Revision as of 12:29, 11 August 2014

Procedure

Operational Safety Procedure (OSP)

Procedure and Checklist

Solenoid Cooldown Checklists
D000000402-P003 Rev A
Solenoid Vacuum System Controls Check Procedure
D000000402P004
Hall D Solenoid System Hi-Pot Procedure
D000000402P006 RevA
Solenoid Voltage Tap Check List
D000000402-P010
Hall D Solenoid Pre Power-Up Checklists
D000000402P007
Hall D Solenoid Magnet Power Supply Maintenance Turn-on Checklist
D000001611P000 Rev A
Hall D Solenoid Magnet Power Supply Internal Interlock Checklist
D000001611P001 Rev B
Ground Fault Detector Rheostat Setting Procedure
D000000402P011
Hall D Solenoid System Hi-Pot Procedure
D000000402P006 RevA
Solenoid Quench Detector Tuning Procedure
[]
  • Magnet Turn-ON Procedure [M:\halld_engineering\Solenoid\Improvements after Aug'13 Test\140617Solenoid turn on trackingTracking.xlsx]
  • Hall D Solenoid Pre Power-Up Checklists Link to Doc Control

Technical Reference

Magnet

Power Supply

Cryogenics System

Programmable Logic Control (PLC)

PXI Fast DAQ System

Quench Detector