Line 4: Line 4:
 
* [http://opsweb.acc.jlab.org/CSUEApps/atlis/task/14423 Link to the accelerator test plan for electron beam commissioning (ATLIS)]
 
* [http://opsweb.acc.jlab.org/CSUEApps/atlis/task/14423 Link to the accelerator test plan for electron beam commissioning (ATLIS)]
 
* Expected duration:  
 
* Expected duration:  
# Sept 19 - Sept ~22: Tune beam to Hall D line dumplette (Tagger Hall can remain open).  
+
# Oct 09 - Octt ~12: Tune beam to Hall D line dumplette (Tagger Hall can remain open).  
# Sept ~22 - Oct 3 2014:  Tune beam to Tagger Hall D  (Tagger Hall and Hall D must be closed).  
+
# Oct ~12 - Oct 22 2014:  Tune beam to Tagger Hall D  (Tagger Hall and Hall D must be closed).  
 
* Prerequisites:
 
* Prerequisites:
 
# Tagger microscope (TAGM) and all the crates with electronics removed from Hall D. <math>\Box</math>
 
# Tagger microscope (TAGM) and all the crates with electronics removed from Hall D. <math>\Box</math>

Revision as of 15:43, 18 September 2014

  1. Oct 09 - Octt ~12: Tune beam to Hall D line dumplette (Tagger Hall can remain open).
  2. Oct ~12 - Oct 22 2014: Tune beam to Tagger Hall D (Tagger Hall and Hall D must be closed).
  • Prerequisites:
  1. Tagger microscope (TAGM) and all the crates with electronics removed from Hall D. \Box
  2. Goniometer in the beam-open position. The goniometer will not be used during the 2014 run.
  3. Amorphous radiator ladder equipped (HARP included) and operational \Box
    • Responsibility: Hovanes Egiyan.
    • Procedure for radiator harp scans
  4. Beam lines under vacuum \Box
  5. Tagger magnet operational \Box
    • Responsibility: MCC
  6. Shielding walls installed \Box
  7. Radiation monitors installed and operational \Box
    • Responsibility: Alexandre Deur (CARMS)/Hovanes Egyian (halo counters)
    • Procedure to monitor CARMs
    • Procedure to monitor Halo Counters
  8. Primary collimator block in the position between two holes, shielding the central area of the beam pipe \Box . Secondary collimator removed.
    • Responsibility: Hovanes Egiyan.
    • Procedure for moving Primary Collimator
  9. First Profiler counter installed in front of the collimator \Box
  10. Second Profiler counter installed in front of photon beam dump \Box
  • Conditions:
  1. Pulsed beam pulsed beam 4-10 µA (average 60-150 nA) for the beam tune
  2. CW beam 50-100 nA at the final stage of the procedure
  3. No radiator inserted. \Box
    • Responsibility: Hovanes Egiyan.
    • Procedure for inserting/removing amorphous radiators
  4. Hall D controlled quadrupole MQPAD00 turned off. \Box
    • Responsibility: MCC
  5. No shift workers in Hall D except for Shift leader if needed and experts from Hall D are involved with the radiation measurements. RC and/or other Hall D personnel follows the beam tuning procedure at the MCC.