# Tagger microscope (TAGM) and all the crates with electronics removed from Hall D. <math>\Box</math>
 
# Tagger microscope (TAGM) and all the crates with electronics removed from Hall D. <math>\Box</math>
 
# Goniometer in the beam-open position. The goniometer will not be used during the 2014 run. <span style="font-size:21px">☑</span>
 
# Goniometer in the beam-open position. The goniometer will not be used during the 2014 run. <span style="font-size:21px">☑</span>
# Amorphous radiator ladder equipped (HARP included) and operational <math>\Box</math>
+
# Amorphous radiator ladder equipped and operational <math>\Box</math>
 
#* Responsibility: Hovanes Egiyan.  
 
#* Responsibility: Hovanes Egiyan.  
#* <span style="color:#ff00ff">Procedure for radiator harp scans </span>
 
 
# Beam lines under vacuum <math>\Box</math>
 
# Beam lines under vacuum <math>\Box</math>
 
# Tagger magnet operational <math>\Box</math>
 
# Tagger magnet operational <math>\Box</math>

Revision as of 07:36, 16 October 2014

  1. 4 days: Tune beam to Hall D line dumplette (Tagger Hall can remain open).
  2. 10 days: Tune beam to Tagger Hall D (Tagger Hall and Hall D must be closed).
  • Prerequisites:
  1. Tagger microscope (TAGM) and all the crates with electronics removed from Hall D. \Box
  2. Goniometer in the beam-open position. The goniometer will not be used during the 2014 run.
  3. Amorphous radiator ladder equipped and operational \Box
    • Responsibility: Hovanes Egiyan.
  4. Beam lines under vacuum \Box
  5. Tagger magnet operational \Box
    • Responsibility: MCC
  6. Shielding walls installed \Box
  7. Radiation monitors installed and operational \Box
    • Responsibility: Alexandre Deur (CARMS)/Hovanes Egyian (halo counters)
    • Procedure to monitor CARMs
    • Procedure to monitor Halo Counters
  8. Primary collimator block in the position between two holes, shielding the central area of the beam pipe \Box . Secondary collimator removed.
    • Responsibility: Hovanes Egiyan.
    • Procedure for moving Primary Collimator
  9. First Profiler counter installed in front of the collimator \Box
  10. Second Profiler counter installed in front of photon beam dump \Box
  • Conditions:
  1. Pulsed beam pulsed beam 4-10 µA (average 60-150 nA) for the beam tune
  2. CW beam 50-100 nA at the final stage of the procedure
  3. No radiator inserted. \Box
    • Responsibility: Hovanes Egiyan.
    • Procedure for inserting/removing amorphous radiators
  4. Hall D controlled quadrupole MQPAD00 turned off. \Box
    • Responsibility: MCC
  5. No shift workers in Hall D except for Shift leader if needed and experts from Hall D are involved with the radiation measurements. RC and/or other Hall D personnel follows the beam tuning procedure at the MCC.