Tune Electron Beam

From Hall D Ops Wiki
Revision as of 08:16, 16 October 2014 by Deurpam (Talk | contribs)

Jump to: navigation, search
  1. 4 days: Tune beam to Hall D line dumplette (Tagger Hall can remain open).
  2. 10 days: Tune beam to Tagger Hall D (Tagger Hall and Hall D must be closed).
  • Prerequisites:
  1. Tagger microscope (TAGM) and all the crates with electronics removed from Hall D. \Box
  2. Goniometer in the beam-open position. The goniometer will not be used during the 2014 run.
  3. Amorphous radiator ladder equipped and operational \Box
    • Responsibility: Hovanes Egiyan.
  4. Beam lines under vacuum \Box
  5. Tagger magnet operational \Box
    • Responsibility: MCC
  6. Shielding walls installed \Box
  7. Radiation monitors installed and operational \Box
  8. Primary collimator block in the position between two holes, shielding the central area of the beam pipe \Box . Secondary collimator removed.
    • Responsibility: Hovanes Egiyan.
    • Procedure for moving Primary Collimator
  9. First Profiler counter installed in front of the collimator \Box
  10. Second Profiler counter installed in front of photon beam dump \Box
  • Conditions:
  1. Pulsed beam pulsed beam 4-10 µA (average 60-150 nA) for the beam tune
  2. CW beam 50-100 nA at the final stage of the procedure
  3. No radiator inserted. \Box
    • Responsibility: Hovanes Egiyan.
    • Procedure for inserting/removing amorphous radiators
  4. Hall D controlled quadrupole MQPAD00 turned off. \Box
    • Responsibility: MCC
  5. No shift workers in Hall D except for Shift leader if needed and experts from Hall D are involved with the radiation measurements. RC and/or other Hall D personnel follows the beam tuning procedure at the MCC.

Back to main Fall14 commissioning page