0000140: Determine requirements for full solenoid control system and design system.
The full solenoid will be tested in Summer 2012. We must redesign the system based on our experience in the Test Lab, and it must account the new cryo system being designed by the Cryo group.
Jonathan Creel is in charge of the new cryo system. He will supply us with details of the control functionality required.
No tags attached.
Issue History
2011-09-21 16:21wolinNew Issue
2011-09-21 16:21wolinWork by outside group for Hall D => No
2011-09-21 16:21wolinEstimated man-weeks => 24
2011-09-21 16:21wolinPercentage complete => 0
2011-09-21 16:21wolinActual man-weeks => 0
2011-10-12 14:48wolinStatusnew => assigned
2011-10-12 14:48wolinAssigned To => wolin
2011-10-12 14:50wolinNote Added: 0000165
2011-10-12 14:50wolinStatusassigned => acknowledged
2012-04-04 15:26wolinSummaryDetermine requirements for full solenoid control system, design and implement => Determine requirements for full solenoid control system and design system.
2012-04-04 15:27wolinNote Added: 0000337
2012-04-04 15:27wolinStatusacknowledged => resolved
2012-04-04 15:27wolinResolutionopen => fixed

Notes
(0000165)
wolin   
2011-10-12 14:50   
A subroup of the Controls group is meeting every two weeks on this. See the Controls wiki for a full list of tasks and questions identified by the subgroup. We need to purchase some equipment to test out some ideas, but alas FY12 12GeV procurements are on hold...
(0000337)
wolin   
2012-04-04 15:27   
Over the past six months we have worked out what needs to be done. Designs are completed or well under way. The test will occur no earlier than Fall 2012.