0000162: Arrange for interim networking and telecom in hall, counting house and trailer
Design networking system. Order large and small switches, arrange for interim telecom and wireless.
Hall D will pay for networking equipment, CC (Bryan et al.) will install and manage it. Analog phones are $35, Ethernet phones are $230. All phones will connect to Telecom room switch, all computers to Rack Room switch in final system, to Telecom room switch for interim networking. Bryan has an analog phone gateway in Telecom room, not sure if we need one in the hall.
No tags attached.
Issue History
2011-11-04 09:25wolinNew Issue
2011-11-04 09:25wolinWork by outside group for Hall D => No
2011-11-04 09:25wolinEstimated man-weeks => 4
2011-11-04 09:25wolinPercentage complete => 0
2011-11-04 09:25wolinActual man-weeks => 0
2011-11-04 09:26wolinStatusnew => assigned
2011-11-04 09:26wolinAssigned To => wolin
2011-11-04 09:29wolinNote Added: 0000195
2011-11-04 09:29wolinStatusassigned => acknowledged
2011-11-15 11:24wolinNote Added: 0000207
2011-11-29 11:52wolinNote Added: 0000218
2011-12-07 11:43wolinNote Added: 0000225
2011-12-20 13:22wolinNote Added: 0000234
2012-01-19 11:37wolinNote Added: 0000241
2012-01-27 10:02wolinNote Added: 0000257
2012-01-27 10:04wolinSummaryArrange for networking and telecom in hall, counting house, tagger building and trailer => Arrange for interim networking and telecom in hall, counting house and trailer
2012-01-27 10:04wolinDescription Updated
2012-01-27 10:04wolinAdditional Information Updated
2012-01-27 10:07wolinNote Added: 0000258
2012-01-27 10:07wolinStatusacknowledged => resolved
2012-01-27 10:07wolinResolutionopen => fixed
2012-01-27 10:34wolinCategoryComputers => Networking

Notes
(0000195)
wolin   
2011-11-04 09:29   
Much work already done on this. Switches are being ordered. Bryan will install fiber trunk between Telecom and Rack rooms. We will install main fiber trunk to platform in hall in about a year, when the platform and cable trays are ready. For interim we'll just install temporary copper cables. Bryan has wireless equipment. Connection to Tagger hall will be via spare "dark fiber" running between Tagger Service building and Counting house.
(0000207)
wolin   
2011-11-15 11:24   
Switches on order, installation planend for Jan 2012, interim wiring and wireless will be used until main cable trunk pulled to platform next summer. Networking available now to switch in Telecom room.
(0000218)
wolin   
2011-11-29 11:52   
Bryan suggests using a small number of subnets in the hall. Perhaps one for high-speed DAQ, another for controls and slow stuff, and use the JLab Desktop subnet in the counting house office area.
(0000225)
wolin   
2011-12-07 11:43   
Bryan says most if not all of our Cisco equipment has arrived. We now have lots of switches!
(0000234)
wolin   
2011-12-20 13:22   
Hovanes and I met with Bryan and Brent. To start we will have three networks in the hall for fast daq, controls and general. Also some computers in the cubicles in the office area will be on the Desktop network.

They will install our big switch in a rack in the rack room just as soon as we get beneficial occupancy. They will install a wireless access point in the hall soon after. We will pull temporary cables to various places in the hall as needed.
(0000241)
wolin   
2012-01-19 11:37   
All five Counting House office area telecom jacks now connected to Telecom room. Tom will install four computers and a printer. Two phones working in office area, will eventually install more phones.

Bryan will get going on running fiber between the Telecom and Rack rooms. UPS should be installed by early Feb, Rack room switch soon after.

Tom will run cable from Telecom room to bottom of truck ramp soon. Brent will install small switch there, Tom will run cable to top of truck ramp, then Brent will install a wireless transceiver aimed at the trailer. Tom will then pray he gets decent reception in trailer, Brent promises nothing!
(0000257)
wolin   
2012-01-27 10:02   
Cables run, wireless in the hall and trailer now working, reception in the trailer not the greatest. Tom is moving the AP outside the building in hopes of improving the situation. Still need to connect the computer running the camera to the new switch.
(0000258)
wolin   
2012-01-27 10:07   
Interim telecom and networking in hall, counting house and trailer now working. Two phones installed in counting house, wireless working in all three locations, printer working in counting house. Will install more computers and phones as needed. Will shift to final networking system within a few months, after components installed.