View Issue Details
0000187Hall D OnlineNetworkingpublic2012-01-27 10:102013-06-14 10:55
wolin 
wolin 
normalfeatureN/A
feedbackopen 
No
4
0
0
0000187: Install final networking system in counting house and hall
Install Hall D switch in Rack Room, move existing interim networking from Telecom switch to Rack Room switch, run fibers from Rack Room to platform in the hall, install small switches as needed in the hall.
No tags attached.
parent of 0000189resolved wolin Install fibers between Telecom and Rack Rooms 
Issue History
2012-01-27 10:10wolinNew Issue
2012-01-27 10:10wolinWork by outside group for Hall D => No
2012-01-27 10:10wolinEstimated man-weeks => 4
2012-01-27 10:10wolinPercentage complete => 0
2012-01-27 10:10wolinActual man-weeks => 0
2012-01-27 10:10wolinStatusnew => assigned
2012-01-27 10:10wolinAssigned To => wolin
2012-01-27 10:11wolinNote Added: 0000259
2012-01-27 10:11wolinStatusassigned => acknowledged
2012-01-27 10:34wolinCategoryComputers => Networking
2012-01-30 16:46wolinNote Added: 0000271
2012-01-30 16:46wolinStatusacknowledged => feedback
2012-01-30 16:47wolinRelationship addedparent of 0000189
2013-03-20 18:02wolinNote Added: 0000493
2013-03-20 18:02wolinStatusfeedback => acknowledged
2013-06-14 10:55wolinNote Added: 0000536
2013-06-14 10:55wolinStatusacknowledged => feedback

Notes
(0000259)
wolin   
2012-01-27 10:11   
Will install components as building, rooms, platform, cable trays and racks become available.
(0000271)
wolin   
2012-01-30 16:46   
Waiting for beneficial occupancy, platforms and cable trays to be installed, etc.
(0000493)
wolin   
2013-03-20 18:02   
Counting house near done, will install fiber networking in the hall when cable trays are in, probably this summer.
(0000536)
wolin   
2013-06-14 10:55   
Waiting for cable trays to be installed and the carriage to be ready.