0000263: Create FastTrack schedule for full solenoid test Fall 2012
Create FastTrack schedule for the test this fall. Start with Josh's schedule.
Tim prefers that everything be included, even Tom's mechanical/installation tasks.
No tags attached.
Issue History
2012-06-05 11:31wolinNew Issue
2012-06-05 11:31wolinWork by outside group for Hall D => No
2012-06-05 11:31wolinEstimated man-weeks => 2
2012-06-05 11:31wolinPercentage complete => 0
2012-06-05 11:31wolinActual man-weeks => 0
2012-06-05 11:31wolinStatusnew => assigned
2012-06-05 11:31wolinAssigned To => wolin
2012-06-05 11:32wolinNote Added: 0000378
2012-06-05 11:32wolinStatusassigned => acknowledged
2012-06-05 11:38wolinReproducibilityhave not tried => N/A
2012-07-10 09:18wolinNote Added: 0000394
2012-07-16 13:14wolinNote Added: 0000401
2012-07-16 13:14wolinStatusacknowledged => resolved
2012-07-16 13:14wolinResolutionopen => fixed

Notes
(0000378)
wolin   
2012-06-05 11:32   
I know about the controls part, will have to get mechanical/installation from someone else.
(0000394)
wolin   
2012-07-10 09:18   
I've done about all I can, time for Tom to really flesh out the mechanical stuff. The FTS is in M:\halld_engineering\Solenoid\Fastrack Schedules\Ready for Cooldown.

Currently pump/purge can start in mid-Dec, cooldown in Jan.
(0000401)
wolin   
2012-07-16 13:14   
Still need Tom's updated mechanical construction timelines and links, but my part is done, at least in terms of entering schedule data. I will continue to update as needed and send out weekly progress summaries.