MantisBT - Hall D Online |
View Issue Details |
|
ID | Project | Category | View Status | Date Submitted | Last Update |
0000090 | Hall D Online | DAQ | public | 2011-06-17 14:48 | 2011-10-31 13:52 |
|
Reporter | wolin | |
Assigned To | heyes | |
Priority | normal | Severity | feature | Reproducibility | N/A |
Status | resolved | Resolution | fixed | |
Platform | | OS | | OS Version | |
Work by outside group for Hall D | Yes |
Estimated man-weeks | 6 |
Percentage complete | 100 |
Actual man-weeks | 2 |
|
Summary | 0000090: Design farm manager CODA component |
Description | Collect requirements and design a monitoring and level 3 farm manager for use in the Hall D Online/DAQ environment. Create prototype and test in simulated but realistic farm environment, if required. Deliver report that summarizes results and includes an outline of steps needed to create and commission production farm manager with estimates of required time and manpower. |
Steps To Reproduce | |
Additional Information | Consult as required with the Hall D Online group concerning the specific requirements and constraints of the Hall D computing system. Major architectural decisions must be reviewed by the Hall D Online group to ensure compatibility with the experiment online environment.
This task is assigned to Vardan, I will keep myself (Heyes) in the "assigned to" field. |
Tags | No tags attached. |
Relationships | |
Attached Files | |
|
Issue History |
Date Modified | Username | Field | Change |
2011-06-17 14:48 | wolin | New Issue | |
2011-06-17 14:48 | wolin | Work by outside group for Hall D | => Yes |
2011-06-17 14:48 | wolin | Estimated man-weeks | => 6 |
2011-06-17 14:48 | wolin | Percentage complete | => 0 |
2011-06-17 14:48 | wolin | Actual man-weeks | => 0 |
2011-06-17 14:49 | wolin | Additional Information Updated | |
2011-06-17 15:25 | wolin | Description Updated | |
2011-06-17 15:44 | wolin | Summary | Create farm manager CODA component => Design farm manager CODA component |
2011-06-20 10:13 | wolin | Status | new => assigned |
2011-06-20 10:13 | wolin | Assigned To | => heyes |
2011-06-20 10:16 | wolin | Note Added: 0000118 | |
2011-06-20 10:18 | wolin | Note Added: 0000124 | |
2011-06-20 10:18 | wolin | Status | assigned => feedback |
2011-07-15 11:16 | heyes | Note Added: 0000144 | |
2011-07-15 11:16 | heyes | Status | feedback => assigned |
2011-07-15 11:16 | heyes | Description Updated | |
2011-07-15 11:16 | heyes | Additional Information Updated | |
2011-10-12 14:55 | wolin | Note Added: 0000170 | |
2011-10-31 13:51 | wolin | Percentage complete | 0 => 100 |
2011-10-31 13:51 | wolin | Actual man-weeks | 0 => 2 |
2011-10-31 13:51 | wolin | Note Added: 0000190 | |
2011-10-31 13:52 | wolin | Note Added: 0000191 | |
2011-10-31 13:52 | wolin | Status | assigned => resolved |
2011-10-31 13:52 | wolin | Resolution | open => fixed |
Notes |
|
(0000118)
|
wolin
|
2011-06-20 10:16
|
|
Graham...kindly review the task description and modify as required, especially the estimated man-weeks of effort needed. We'll iterate as needed. |
|
|
(0000124)
|
wolin
|
2011-06-20 10:18
|
|
Please update task description as needed |
|
|
(0000144)
|
heyes
|
2011-07-15 11:16
|
|
I don't know where the man week estimate came from but it will be updated after preliminary discussions of scope and priority are complete.
I removed the text "CODA component" from the description. It may be that the farm manager is a framework based on a combination of AFECS, ET and CMSG. Maybe even some online adaptation of CLARA. |
|
|
(0000170)
|
wolin
|
2011-10-12 14:55
|
|
Vardan is about done with the planning/prototyping, final report within the next week or so expected. Next task for Vardan will be the Experiment Control Supervisor and GUI. |
|
|
(0000190)
|
wolin
|
2011-10-31 13:51
|
|
Vardan's final report is in the DocDB number 1857. |
|
|
(0000191)
|
wolin
|
2011-10-31 13:52
|
|
Vardan submitted his final report |
|