IDProjectCategoryView StatusDate SubmittedLast Update
0000189Hall D OnlineNetworkingpublic2012-01-27 10:172013-03-19 12:00
Reporterwolin 
Assigned Towolin 
PrioritynormalSeverityfeatureReproducibilityN/A
StatusresolvedResolutionfixed 
PlatformOSOS Version
Summary0000189: Install fibers between Telecom and Rack Rooms
DescriptionMain connection between our switch and the JLab backbone networking system.
Additional InformationOriginally was included in the 12GEV civil contract but got cut out. We may have to pay for it. Latest quote from Shields was over $8k.
TagsNo tags attached.
Work by outside group for Hall DNo
Estimated man-weeks1
Percentage complete0
Actual man-weeks0
Attached Files

- Relationships
child of 0000187feedbackwolin Install final networking system in counting house and hall 

-  Notes
(0000262)
hovanes (manager)
2012-01-27 10:49

The online schedule is being updated to allocate enough money for fiber installations in the counting house itself. The activity line number is going to be 1531048.
(0000263)
wolin (administrator)
2012-01-27 11:17

From Hovanes:

We are adding 10K to the schedule, activity line 1531048. Hopefully, it gets approved, but we should wait for approval. We are not installing the switch right now anyway. Please, make sure it gets charged to "12CDAQ.12GEV" POA, with "Activity line 1531048" in the Notes for PR.
(0000306)
wolin (administrator)
2012-02-08 15:42
edited on: 2012-02-08 16:14

Dianne says no problem with getting fibers, few day installation. Brian says prior to installing the fibers we just need the Telecom rack installed, no need for power, and he prefers that the switch go in after the fibers.

(0000363)
wolin (administrator)
2012-04-24 15:07

Waiting for UPS to be installed, then for power distribution installation under the floor. Then we can move the racks in and install the fibers.
(0000381)
wolin (administrator)
2012-06-05 11:41

Waiting for counting house rack room power to be ready and racks installed, meanwhile we get temporary networking from the Telecom room switch.
(0000423)
wolin (administrator)
2012-08-08 14:46

Power and racks in Rack Room should be complete by early Sep. I contacted Bryan Hess and asked that he plan to install the fibers (and our network switch) in mid-Sep, assuming all goes well with the electrical and mechanical work.
(0000438)
wolin (administrator)
2012-09-11 13:56

Jason got a quote from Shields, $8k!!! Why so much?
(0000480)
wolin (administrator)
2013-03-19 12:00

This was completed a while ago.

- Issue History
Date Modified Username Field Change
2012-01-27 10:17 wolin New Issue
2012-01-27 10:17 wolin Work by outside group for Hall D => No
2012-01-27 10:17 wolin Estimated man-weeks => 1
2012-01-27 10:17 wolin Percentage complete => 0
2012-01-27 10:17 wolin Actual man-weeks => 0
2012-01-27 10:17 wolin Status new => assigned
2012-01-27 10:17 wolin Assigned To => hovanes
2012-01-27 10:34 wolin Category Computers => Networking
2012-01-27 10:49 hovanes Note Added: 0000262
2012-01-27 10:49 hovanes Assigned To hovanes => wolin
2012-01-27 11:17 wolin Note Added: 0000263
2012-01-27 11:17 wolin Status assigned => acknowledged
2012-01-30 16:47 wolin Relationship added child of 0000187
2012-02-08 15:42 wolin Note Added: 0000306
2012-02-08 16:14 wolin Note Edited: 0000306
2012-04-24 15:07 wolin Note Added: 0000363
2012-06-05 11:41 wolin Note Added: 0000381
2012-06-05 11:41 wolin Status acknowledged => feedback
2012-08-08 14:46 wolin Note Added: 0000423
2012-08-08 14:46 wolin Status feedback => assigned
2012-09-11 13:56 wolin Note Added: 0000438
2012-09-11 13:58 wolin Status assigned => acknowledged
2013-03-19 12:00 wolin Note Added: 0000480
2013-03-19 12:00 wolin Status acknowledged => resolved
2013-03-19 12:00 wolin Resolution open => fixed