OWG Meeting 28-Oct-2009

From GlueXWiki
Jump to: navigation, search

Agenda

This will be a short meeting as we have interviews at 2:30pm

  • Announcements -
  • Review of minutes from 30-Sep-2009 meeting
  • Electronics update - Fernando (he has another meeting at 2pm)
  • Report on SSP - Ben
  • Other electronics and trigger status reports - Chris, Ben, Ed, Alex, Dave


Time/Location

1:30 PM Wed 28-Oct-2009 CC F326


Announcements

Next Meeting

1:30 PM Wed 11-Nov-2009


New Action Items from this Meeting

Minutes

Attendees: Elliott W, Mark I, Chris, C, Ben R, Simon T, William G, Fernando B, Beni Z.


SSP Board Design

Ben gave a brief overview of progress on SSP board design.

  • Front panel includes NIM and differential inputs.
  • 8 fiber transceivers per board.
  • CLAS will use a different version of the board, one SSP per sector.
  • Board layout is preliminary, all major components placed, minor ones not placed yet.
  • Firmware has been simulated.


ASIC and SiPM Update

Fernando gave an update on the ASIC preamp and SiPM efforts. See GlueX docs 1364 (ASIC) and 1370 (SiPM).

  • ASIC and board ready for production, all features included (incl. dual gain).
  • Boards pass all tests, look very good.
  • Have 40 new ASICS with correct wire bonding plus old ones with faulty bond.
  • Need 2000 for final system.
  • Hamamatsu has delivered 10 4x4 SiPM arrays (1.2 cm square), still waiting for SensL (deadline early Nov).
  • Ceramic carrier, no cooling needed, but temperature stabilization needed.
  • 81% coverage, SensL will be slightly less.
  • 50 micron pixels.
  • Initial testing very good, meets all specs, cost in our range.
  • Large SiPM array capacitance is typically high, not much can be done about it.
  • Get 13 ns risetime for 5 ns input, 76 ns width.
  • Carl Zorn will perform extensive tests on all 10 SiPM's.
  • Gain about 10**6, noise ok.


Electronics Update

Chris gave an update on the remaining electronics efforts.

  • All projects well defined and moving along according to schedule, manpower ok.
  • Version 2 of TDC and ADC coming up, serious work to begin by March 2010.
  • Work on global trigger boards (GTP, SSP) in progress.
  • TS board will be worked on in the next fiscal year, DAQ group heavily involved.
  • Chris is working on early VXS crate procurement for all halls, order perhaps in Spring 2010.