Difference between revisions of "July 9, 2024 KLONG KPT post Review Design Meeting"

From GlueXWiki
Jump to: navigation, search
(Minutes/Actions)
(Minutes/Actions)
Line 30: Line 30:
 
* Keith to send out updated layout in a few days from the meeting
 
* Keith to send out updated layout in a few days from the meeting
 
* Once layout is deemed good, we can start procuring items - we have about $100K to spend this fiscal year
 
* Once layout is deemed good, we can start procuring items - we have about $100K to spend this fiscal year
 +
* Thermal cycling analysis for tungsten, beryllium and copper submitted to Patrizia
  
 
== Action Items ==
 
== Action Items ==

Revision as of 15:07, 11 July 2024

Meeting Time and Place

Tuesday July 9, 2024, 1:30pm

  • Invited - Hovanes Egiyan, Stephanie Worthington, Keith Harding, Igor Strakovsky, Tim Whitlatch, Vitaly Baturin, Eugene Chudakov, Josh Ballard, Amaryan Moskov

Agenda

Minutes/Actions

  • Plan for removing (decommission) KPT is to use Airpad casters that we procure for the CPS install
    • Will need to mend path between concrete and steel at cave entrance (sheet metal will do)
  • Need to extend rails to be able to move KPT assy north when going back to GlueX
  • Concern with radiation on 10" Kapton window - can replace with aluminum (maybe 0.5mm thk) (Tim to look at this)
  • Need to move items upstream to make room for Profiler and new Active collimator
    • KPT assy move a few inches downstream
    • 2nd concrete wall moved 6" downstream to make allyway 34" wide (hopefully confined space permit not needed)
    • Permanent magnet moved 6" downstream (beampipe through wall will need to be installed before magnet)
    • Profiler needs to be moved as far from beamline as possible and shielded when not in use
  • Discussed cooling/Power failure
    • Use temperature trip for beam "FSD"
    • Still need to write FMEA before ERR next year
  • Need to have RADCON approve designs before ERR
  • 98.5% beryllium ok for target
  • 95% tungsten ok for absorber
  • Keith to send out updated layout in a few days from the meeting
  • Once layout is deemed good, we can start procuring items - we have about $100K to spend this fiscal year
  • Thermal cycling analysis for tungsten, beryllium and copper submitted to Patrizia

Action Items