Difference between revisions of "CPP Test 2020 - Schedule"
From GlueXWiki
(→Test sequence) |
(→CPP Preliminary baseline measurements) |
||
Line 24: | Line 24: | ||
=== CPP Preliminary baseline measurements=== | === CPP Preliminary baseline measurements=== | ||
− | These will be conducted by Ilya during | + | These will be conducted by Ilya during Sat Aug 29 4am-10am shift. |
# CPP test DAQ setup: 2 hrs | # CPP test DAQ setup: 2 hrs | ||
# Set coherent peak to 6 GeV | # Set coherent peak to 6 GeV |
Revision as of 10:11, 28 August 2020
Detector configurations
Nominal GlueX configuration
- No Pb shielding
- DIRC installed
- Solenoid field at 1350 A
- Radiator Diamond JD70-105 47 um, Peak at 8.6 GeV
CPP Test Configuration
- With and without Pb shielding
- DIRC removed
- Solenoid field at 1350 A (no change)
- Radiator Diamond JD70-105 47 um, Peak at 6 GeV
Test layout
Screenshots of test layout media:CPP_Testconfig.jpg media:CPP_Testconfig2.jpg media:CPP_Testconfig3.jpg media:CPP_Testconfig4.jpg media:CPP_Testconfig5.jpg media:CPP_Testconfig6.jpg
Test sequence
Possible test schedule by Tim Media:CPP_Tests_Aug2020.pdf
Total estimated time for test including installation, data taking and reinstallation of GlueX is 34 hours.
CPP Preliminary baseline measurements
These will be conducted by Ilya during Sat Aug 29 4am-10am shift.
- CPP test DAQ setup: 2 hrs
- Set coherent peak to 6 GeV
- Data GlueX configuration - Full Target/DIRC (repeat from Dec 2019): 2 hrs
- Empty target : 1 hr
- Data GlueX configuration - Empty Target/DIRC : 1 hr
- Restore coherent peak to 8.6 GeV
Installation/setup of CPP Test
- Pass change for Hall A/C Day Mon Aug 31
- Configure experiment for CPP Test: 12 hr. Mark Stevens and staff.
- Training for Pb sheet install/removal?
CPP Test. Mon evening Aug 31 - Tue morning Sep 1
- Fill Target :
- Install 1 Pb sheet: 1 hr
- Data CPP Test configuration- Full Target/no DIRC/1Pb : 1 hr
- Install 0 Pb sheet: 1 hr
- Data CPP Test Configuration - Full Target/no DIRC/ 0Pb : 1 hr
- Install 2 Pb sheets: 1 hr
- Data CPP Test Configuration - Full Target/no DIRC/2Pb : 1 hr
- Empty Target :
- Install 1 Pb sheet: 1 hr
- Data CPP Test configuration- Empty Target/no DIRC/1Pb : 1 hr
- Install 0 Pb sheet: 1 hr
- Data CPP Test Configuration - Empty Target/no DIRC/0Pb : 1 hr
- Install 2 Pb sheets: 1 hr
- Data CPP Test Configuration - Empty Target/no DIRC/2Pb : 1 hr
Restore GlueX configuration and prepare for GEM-TRD Test. Tue day Sep 1
- Fill Target
- Restore nominal GlueX configuration: 4 hours.
Required personnel
- Two persons needed to install/remove Pb Sheets
- Mark Dalton has volunteered to come in on Monday evening if a third person is required to monitor the target.
Date | Shift | Worker | CPP |
---|---|---|---|
Mon Aug 31 | 4 pm - 10 pm | T. Britton | D. Lawrence |
Mon Aug 31 | 10 pm - 4 am | S. Furletov | I. Larin |
Tue Sep 01 | 4 am - 10 am | M. Khachatryan | E. Smith |
DIRC survey
- The DIRC will have to be surveyed following the test.