+ | * tagger NMR probe not operational.[https://logbooks.jlab.org/entry/4009229 TAGGER NMR] | ||
+ | |||
=== Plans === | === Plans === | ||
Revision as of 17:58, 30 June 2022
Back to Run Coordination Meetings:Summer2022
Meeting are via ZoomGov: connect (Meeting ID: 160 199 0060 / Passcode 8394)
Hall D counting room white board
Contents
Friday July 1
Past 24 hours
- start out with no beam. Beam lost due to 1L15. whole day shift needed to replace "braker" for zone 1L15
- after accelerator repair work, efforts are taken to establish beam in the machine and try to increase beam current for HallC
- Bobby and Ilya entered to hall to investigate the target moving mechanism.
- Justin rebooted crate U1-1-top to reestablish BCAL LED trigger
- the magnetic field measurement of the tagger magnet is still not working. See earlier report
Shift reports
Reports
- low invariant mass +/- pair tracks are indeed leptons: E/p vs Mass
- target position mechanism and small variations:
- tbd
Issues
- tagger NMR probe not operational.TAGGER NMR
Plans
Thursday June 30
Past 24 hours
Overarching theme of the past 24 hours: "herding cats"
- no beam during the day, machine optimization to deliver high current beam to HallC (unsuccessful)
- beam back around 5:30pm
- did first two Harp scans with HallD laser on and off while hallC had around 17uA of beam
- Scan One with our beam
- Scan Two only HallC beam
- Scan results at collimator
- peak to base line of the harp peaks is about 100 (as in previous scans)
- OLD harp scan from Dec 1 2021 and Dec 2 2021
- general beam conditions are rather unstable. beam strip chart
- continue data taking over night
- DAQ issues again with life time dropping to 60%. Shift crew called Sergey.
- found problem with Slot 3 fiber 7 having trouble (I think this is seen in roctrig1?)
- after Sergey's intervention DAQ came slowly back to "normal"
- beam conditions are very unstable over night
- Loss of NMR comm in Tagger Manet
- again very bad life time 10% only! (stopped run 100778) but also beam lost beam at the same time.
- stopping and restarting the DAQ with new run 100779 cured the issue of low lifetime, but soon beam was lost again.
- beam on and off for some time, finally off with problems in several cavities one whole (1L15) zone no beam for several hours.
Shift reports
Reports
- invariant mass of pi+pi- tracks: Vertex VS M(pi+pi-)
- follow up Energy, Trigger Bit
Issues
- HallD beam conditions(e,gamma): quality/stability
- Tuned beam and CW beam to hallD looks different ELOG entry
- HallC beam high current not reached, current reached 30uA
Plans
- MCC: Machine needs to replace "breaker" in 1L15
- last time this work took about 6 hours
- NL and SL to be taken down
- take this opportunity to assess relocation of some BLM in the machine
- expect beam no earlier then swing shift.
- CPP/NPP: TBD
- first do harp scans when beam comes back
- do first an Amo run using goniometer Al radiator if that does not work due to ion chamber try target ladder Al radiator.
- continue nominal production data taking on diamond.