Difference between revisions of "Run Planning Meeting Notes, August 11- August 17, 2022"
From GlueXWiki
(→Reports) |
(→Friday: Day through Owl) |
||
Line 64: | Line 64: | ||
= Monday August 14 = | = Monday August 14 = | ||
== Friday: Day through Owl == | == Friday: Day through Owl == | ||
− | * at 7:45 am meeting Hall B complained about | + | * at 7:45 am meeting Hall B complained about bleedthrough from C; optimizing the machine led to considerable downtime during the day. |
* at 12 pm MCC starts tuning | * at 12 pm MCC starts tuning | ||
− | |||
<!-- * [https://logbooks.jlab.org/entry/4027490 Program Deputy summary] --> | <!-- * [https://logbooks.jlab.org/entry/4027490 Program Deputy summary] --> | ||
− | * | + | * Otherwise running on Pb target (30 nA) |
{| class=wikitable | {| class=wikitable |
Revision as of 17:28, 13 August 2022
Back to Run Coordination Meetings:Summer2022
Meeting are via ZoomGov: connect (Meeting ID: 160 199 0060 / Passcode 8394)
Hall D counting room white board
Thursday August 11
Past 24 hours
- Running on Pb target (30 nA). Another relatively good day: ABU=18.3 h for the day
- Beam down for 3.75 hrs due to afternoon thunderstorms
- Program Deputy summary
Shift Reports
- Day shift summaries (1), (2)
- Swing shift summary (1), (2)
- Owl shift summary
- Early Riser shift summary
Reports
Issues
- Continued: TAGH major link alarm. Description by shift leader. Cannot communicate with crate, but rates are fine -> we decided to run as it is (monitoring TAGH scalars with stripcharts) and have a look latter.
Plans
- Beam off all day for maintenance day
- Hall in controlled access
- Solenoid current to be lowered because of cryowork. Tim seems to be doing this from home as we speak.
- Requested survey of tagger hall for access to reset TAGH crate
- When beam restored run harp scans
- Production on Pb target.
- Next pass change (4->3) for Hall C will be Tuesday. They will be down for 6h-8h Monday to install their aerogel. Monday is auspicious for a TAC run.
Friday August 12
Past 24 hours
- Beam off Thu 630 am - ?? pm for maintenance day
- ~ 9 am access to tagger hall by Beni to reset TAGH HV crate; OK now
- ramped down solenoid for cry work (Tim)
- resume prodcution data Friday 3:18 am
Shift Reports
Reports
- Beni reset the TAGH HV crate; it's communicating again ([1])
- Malte changed 2 FCAL bases ([2], [3])
- The filter material (Molecular Sieve) Assy. for the Cryomech cold compressor in Hall-D has been completed by target group
- Tim also reports that compressor swap is complete; not sure whether that refers to the target group's work?
- Beam delivary after maintenance day delayed until ??? due to a leak in magnet LCW hose in NL.
Issues
Plans
- Continue with prodcution data on Pb through the weekend.
- Plan for TAC run on Monday, when Hall C installs their aerogel.
Monday August 14
Friday: Day through Owl
- at 7:45 am meeting Hall B complained about bleedthrough from C; optimizing the machine led to considerable downtime during the day.
- at 12 pm MCC starts tuning
- Otherwise running on Pb target (30 nA)
Shift | ABU | BANU | BNA | ER |
---|---|---|---|---|
8/12 Day | 4.24 h | 3.3 min | 3.70 h | 8 h |
8/12 Swing | 2.97 h | 1.40 h | 3.63 h | 8 h |
8/13 Owl | 6.49 h | 0.30 h | 1.20 h | 7.93 h |
Total | 13.70 h | 1.76 h | 8.53 h | 23.93 h |
Shift Reports
Reports
- Harp scans: IHA5C11, IHA5C11B, our harp, convergence fits; looks very good, much better than scans from last night.