Line 10: Line 10:
  
 
* FastTrack schedule status - George, Chuck
 
* FastTrack schedule status - George, Chuck
 +
* Status of controls drawings and wiring lists - Scot
 
* Finalizing P&I diagram - George, Elliott
 
* Finalizing P&I diagram - George, Elliott
 
* Coil 1 cryostat testing status - George
 
* Coil 1 cryostat testing status - George

Revision as of 09:51, 23 December 2009

Solenoid Coil Test Weekly Meeting

Location and Time

  • Thu 7-Jan-2010 9:45 am ARC 428


Agenda

  • FastTrack schedule status - George, Chuck
  • Status of controls drawings and wiring lists - Scot
  • Finalizing P&I diagram - George, Elliott
  • Coil 1 cryostat testing status - George
  • Construction/installation sequence drawings - George
  • Power narrative to Mark W - George
  • Status of PLC programming - Mark W
  • Alarm system and paging - Elliott
  • Final decision on power supply dump resistor - Mark S
  • Arrange for electrical work in Test Lab - Tom
  • Arrange for telecom in Test Lab - Elliott
  • Arrange for networking in Test Lab - Elliott
  • GN2 vent piping system - Tom
  • QWeak area, bigger door in F117 - Tom
  • What controls equipment still hasn't arrived - Scot
  • Wiring progress in F117 - Scot
  • Locating computer in SRF control room - Elliott
  • Backup computer - Elliott
  • Status of interface to cryo can - George
  • Status of pressure relief system design - George
  • Status of ordering cryo can - George
  • Coil 1 modification and testing - George
  • Coil 2 cost and schedule - George
  • Coil 3 statement of work, visit and IUCF contract - George, Tom
  • Coil 4 controls wiring replacement - George
  • Shipping rails and transportainer from IUCF - Chuck
  • Safety reviews: when to start formal process - George, Elliott
  • 5 G contours - George