Difference between revisions of "Coil Test Weekly Meeting 7-Jan-2010"
From GlueXWiki
m |
m |
||
Line 10: | Line 10: | ||
* FastTrack schedule status - George, Chuck | * FastTrack schedule status - George, Chuck | ||
+ | * Status of controls drawings and wiring lists - Scot | ||
* Finalizing P&I diagram - George, Elliott | * Finalizing P&I diagram - George, Elliott | ||
* Coil 1 cryostat testing status - George | * Coil 1 cryostat testing status - George |
Revision as of 09:51, 23 December 2009
Solenoid Coil Test Weekly Meeting
Location and Time
- Thu 7-Jan-2010 9:45 am ARC 428
Agenda
- FastTrack schedule status - George, Chuck
- Status of controls drawings and wiring lists - Scot
- Finalizing P&I diagram - George, Elliott
- Coil 1 cryostat testing status - George
- Construction/installation sequence drawings - George
- Power narrative to Mark W - George
- Status of PLC programming - Mark W
- Alarm system and paging - Elliott
- Final decision on power supply dump resistor - Mark S
- Arrange for electrical work in Test Lab - Tom
- Arrange for telecom in Test Lab - Elliott
- Arrange for networking in Test Lab - Elliott
- GN2 vent piping system - Tom
- QWeak area, bigger door in F117 - Tom
- What controls equipment still hasn't arrived - Scot
- Wiring progress in F117 - Scot
- Locating computer in SRF control room - Elliott
- Backup computer - Elliott
- Status of interface to cryo can - George
- Status of pressure relief system design - George
- Status of ordering cryo can - George
- Coil 1 modification and testing - George
- Coil 2 cost and schedule - George
- Coil 3 statement of work, visit and IUCF contract - George, Tom
- Coil 4 controls wiring replacement - George
- Shipping rails and transportainer from IUCF - Chuck
- Safety reviews: when to start formal process - George, Elliott
- 5 G contours - George
- Coil Test Top To-Do items