Difference between revisions of "Coil Test Weekly Meeting 21-Jan-2010"
From GlueXWiki
m |
m |
||
(2 intermediate revisions by the same user not shown) | |||
Line 10: | Line 10: | ||
* Safety narrative and PLC programming strategy - Elliott | * Safety narrative and PLC programming strategy - Elliott | ||
+ | ** preparation for safety reviews | ||
* P&I diagram including machine protection systems - George, Josh, Scot, Elliott | * P&I diagram including machine protection systems - George, Josh, Scot, Elliott | ||
* Final narrative including cryo, power, safety, machine protection, fault diagnosis - George | * Final narrative including cryo, power, safety, machine protection, fault diagnosis - George | ||
Line 17: | Line 18: | ||
* Status of items on George's punch list - George | * Status of items on George's punch list - George | ||
* Yoke fillers - George | * Yoke fillers - George | ||
+ | * GN2 vent piping system tie-in - Mark S | ||
* When do we start installing things in Test Lab - Tom | * When do we start installing things in Test Lab - Tom | ||
** delivery dates of platform stand, cryo can, IUCF items, etc. | ** delivery dates of platform stand, cryo can, IUCF items, etc. | ||
+ | * What PLC display pages do we want, and what should be archived and how often - George | ||
+ | ** main pages, fault pages, trends, etc. | ||
* FastTrack schedule status - George, Chuck | * FastTrack schedule status - George, Chuck | ||
* Coil 1 cryostat testing status - George | * Coil 1 cryostat testing status - George | ||
Line 29: | Line 33: | ||
* Arrange for telecom in Test Lab - Elliott | * Arrange for telecom in Test Lab - Elliott | ||
* Arrange for networking in Test Lab - Elliott | * Arrange for networking in Test Lab - Elliott | ||
− | |||
* QWeak area, bigger door in F117 - Tom | * QWeak area, bigger door in F117 - Tom | ||
* Locating computer in SRF control room - Elliott | * Locating computer in SRF control room - Elliott |
Latest revision as of 16:34, 19 January 2010
Solenoid Coil Test Weekly Meeting
Location and Time
- Thu 21-Jan-2010 9:45 am ARC 428
Agenda
- Safety narrative and PLC programming strategy - Elliott
- preparation for safety reviews
- P&I diagram including machine protection systems - George, Josh, Scot, Elliott
- Final narrative including cryo, power, safety, machine protection, fault diagnosis - George
- Status of PLC programming - Mark W
- Status of controls drawings and wiring lists - Scot
- Wiring progress in F117 - Scot
- Status of items on George's punch list - George
- Yoke fillers - George
- GN2 vent piping system tie-in - Mark S
- When do we start installing things in Test Lab - Tom
- delivery dates of platform stand, cryo can, IUCF items, etc.
- What PLC display pages do we want, and what should be archived and how often - George
- main pages, fault pages, trends, etc.
- FastTrack schedule status - George, Chuck
- Coil 1 cryostat testing status - George
- Coil 1 status - George
- Coil 2 cost and schedule - George
- Coil 3 statement of work, visit and IUCF contract - George, Tom
- Coil 4 controls wiring replacement - George
- Shipping rails and transportainer from IUCF - Chuck
- Arrange for electrical work in Test Lab - Tom
- Arrange for telecom in Test Lab - Elliott
- Arrange for networking in Test Lab - Elliott
- QWeak area, bigger door in F117 - Tom
- Locating computer in SRF control room - Elliott
- Backup computer - Elliott
- Safety reviews: when to start formal process - George, Elliott
- 5 G contours - George
- Coil Test Top To-Do items