Difference between revisions of "Minutes-3-25-2010"
From GlueXWiki
(→Tentative Agenda) |
(→Tentative Agenda) |
||
Line 16: | Line 16: | ||
#* tension specs | #* tension specs | ||
# Full scale prototype tests | # Full scale prototype tests | ||
− | #* lessons learned from the HV tests [[Media:wire_signal_issues.pdf | cope shots1]] [[Media:wire_signal_issues1.pdf | cope shots2]] | + | #* lessons learned from the HV tests [[Media:wire_signal_issues.pdf | cope-shots1]], [[Media:wire_signal_issues1.pdf | cope-shots2]] |
#* plans for tests in the tend | #* plans for tests in the tend | ||
#* some results from the tests with Sr source [http://www.jlab.org/Hall-D/detector/fdclog/ FDC Log Book] (Lubomir) | #* some results from the tests with Sr source [http://www.jlab.org/Hall-D/detector/fdclog/ FDC Log Book] (Lubomir) |
Revision as of 09:17, 25 March 2010
March 25, 2010 FDC meeting
Tentative Agenda
- Production space update off-site floor plans
- Electronics
- threshold variations in the discriminator section of the pre-amps (Fernando)
- PCB status
- Frame modification work
- cathode sandwich and wire frame
- ground plane tests (leakage, tension)
- Wire winding update
- IUCF phase 3 contract
- plans for wire winding upgrades in the summer
- tension specs
- Full scale prototype tests
- lessons learned from the HV tests cope-shots1, cope-shots2
- plans for tests in the tend
- some results from the tests with Sr source FDC Log Book (Lubomir)
- Cathode frame redesign
- MC studies of the beam hole size (Alex)
- Other
- wire sample measurements wire sample reports
- updated FDC naming convention naming convention