Difference between revisions of "Coil Test Weekly Meeting 6-May-2010"
From GlueXWiki
m |
m |
||
Line 18: | Line 18: | ||
* Wiring and testing controls racks - Scot, Mark S | * Wiring and testing controls racks - Scot, Mark S | ||
** "cheater boxes" | ** "cheater boxes" | ||
− | ** | + | ** when to move PLC from ARC 101 to F117 |
− | * | + | * PLC programming status - Mark W |
** Lakeshore calibrations | ** Lakeshore calibrations | ||
+ | ** Impact of additional RS232 and other devices | ||
* HMI and EWEB programming - Yi, Elliott | * HMI and EWEB programming - Yi, Elliott | ||
− | ** | + | ** status of developing display pages and archiving |
+ | ** offsite visibility of EWEB pages | ||
* EPICS connection to PLC - Elliott, Wesley | * EPICS connection to PLC - Elliott, Wesley | ||
* Installation progress - George | * Installation progress - George |
Revision as of 10:00, 4 May 2010
Solenoid Coil Test Weekly Meeting
Location and Time
- Thu 6-May-2010 9:30am ARC 428
Agenda
- Safety review - OSP and COO - Elliott, Josh, Tim
- subject matter experts
- what drawings are needed - final P&I, wiring diagrams, etc.
- what documents are needed - writing assignments
- next meeting with Bob May et al.
- Review of instrumentation controllers and final controls equipment order - Elliott
- Failure analysis, machine protection, safety interlocks - Scot, Mark S, Josh, Elliott
- Wiring and testing controls racks - Scot, Mark S
- "cheater boxes"
- when to move PLC from ARC 101 to F117
- PLC programming status - Mark W
- Lakeshore calibrations
- Impact of additional RS232 and other devices
- HMI and EWEB programming - Yi, Elliott
- status of developing display pages and archiving
- offsite visibility of EWEB pages
- EPICS connection to PLC - Elliott, Wesley
- Installation progress - George
- Coil 1 status - George
- Coil 2 status - George
- Coil 3 repairs at IUCF - George