Difference between revisions of "Coil Test Weekly Meeting 6-May-2010"
From GlueXWiki
m |
m |
||
(7 intermediate revisions by the same user not shown) | |||
Line 9: | Line 9: | ||
'''Agenda''' | '''Agenda''' | ||
+ | * How might we use FEL people? - George, Elliott | ||
+ | * Could we use a summer student? - Elliott | ||
* Safety review - OSP and COO - Elliott, Josh, Tim | * Safety review - OSP and COO - Elliott, Josh, Tim | ||
** subject matter experts | ** subject matter experts | ||
− | ** what drawings are needed - final P&I, etc. | + | ** what drawings are needed - final P&I, wiring diagrams, etc. |
** what documents are needed - writing assignments | ** what documents are needed - writing assignments | ||
− | ** next meeting with Bob May | + | ** next meeting with Bob May et al. |
− | * | + | * Review of instrumentation controllers and final controls equipment order - Elliott |
− | * Failure analysis | + | * Failure analysis, machine protection, safety interlocks - Scot, Mark S, Josh, Elliott |
* Wiring and testing controls racks - Scot, Mark S | * Wiring and testing controls racks - Scot, Mark S | ||
− | ** | + | ** "cheater boxes" |
− | + | ** when to move PLC from ARC 101 to F117 | |
− | * | + | * PLC programming status - Mark W |
** Lakeshore calibrations | ** Lakeshore calibrations | ||
− | * HMI and EWEB programming | + | ** Impact of additional RS232 and other devices |
− | ** | + | * HMI and EWEB programming - Yi, Elliott |
+ | ** status of developing display pages and archiving | ||
+ | ** offsite visibility of EWEB pages | ||
* EPICS connection to PLC - Elliott, Wesley | * EPICS connection to PLC - Elliott, Wesley | ||
+ | * [http://opsweb.acc.jlab.org/CSUEApps/elog/elog.php?logbook=HDCOILTEST Accelerator elog] for coil test - Elliott | ||
* Installation progress - George | * Installation progress - George | ||
* Coil 1 status - George | * Coil 1 status - George | ||
* Coil 2 status - George | * Coil 2 status - George | ||
* Coil 3 repairs at IUCF - George | * Coil 3 repairs at IUCF - George |
Latest revision as of 15:46, 5 May 2010
Solenoid Coil Test Weekly Meeting
Location and Time
- Thu 6-May-2010 9:30am ARC 428
Agenda
- How might we use FEL people? - George, Elliott
- Could we use a summer student? - Elliott
- Safety review - OSP and COO - Elliott, Josh, Tim
- subject matter experts
- what drawings are needed - final P&I, wiring diagrams, etc.
- what documents are needed - writing assignments
- next meeting with Bob May et al.
- Review of instrumentation controllers and final controls equipment order - Elliott
- Failure analysis, machine protection, safety interlocks - Scot, Mark S, Josh, Elliott
- Wiring and testing controls racks - Scot, Mark S
- "cheater boxes"
- when to move PLC from ARC 101 to F117
- PLC programming status - Mark W
- Lakeshore calibrations
- Impact of additional RS232 and other devices
- HMI and EWEB programming - Yi, Elliott
- status of developing display pages and archiving
- offsite visibility of EWEB pages
- EPICS connection to PLC - Elliott, Wesley
- Accelerator elog for coil test - Elliott
- Installation progress - George
- Coil 1 status - George
- Coil 2 status - George
- Coil 3 repairs at IUCF - George