Difference between revisions of "Coil Test Weekly Meeting 5-Aug-2010"

From GlueXWiki
Jump to: navigation, search
 
m
Line 9: Line 9:
 
'''Agenda'''
 
'''Agenda'''
  
* Vacations - All
+
* Vacations
 
** Test Lab power and cryo not available 14-30 Aug, no cryo connections either!
 
** Test Lab power and cryo not available 14-30 Aug, no cryo connections either!
 
** get OSP and go cold early Sep?
 
** get OSP and go cold early Sep?

Revision as of 14:27, 2 August 2010

Solenoid Coil Test Weekly Meeting

Location and Time

  • Thu 29-Jul-2010 9:30am ARC 428


Agenda

  • Vacations
    • Test Lab power and cryo not available 14-30 Aug, no cryo connections either!
    • get OSP and go cold early Sep?
  • Test plan - Josh
    • tags, HMI, etc.
  • Telephone - Elliott
  • Magnet power supply and interlock commissioning - Cody
    • flow pressures and rates
    • filters?
    • interlock on strain gauges?
  • Controls racks - Scot
  • PLC programming/testing status - Mark W
    • backup PLC programmer?
  • UPS status - Mark W, Elliott
    • relay modules, use in interlock system
    • connection to PLC?
  • EPICS <--> PLC communications - Wesley, Elliott
    • connection to guard shack
  • HMI and EWEB programming - Yi, Elliott
  • Installation status - George, Mark S
    • cryo can, platform and stand
    • Two weeks notice to Errol - when?
    • backup power in Test Lab?
  • Coil repair status - George
  • OSP documents and review - Elliott, George