Difference between revisions of "Coil Test Weekly Meeting 5-Aug-2010"
From GlueXWiki
m |
|||
Line 9: | Line 9: | ||
'''Agenda''' | '''Agenda''' | ||
− | * Vacations | + | * Vacations |
** Test Lab power and cryo not available 14-30 Aug, no cryo connections either! | ** Test Lab power and cryo not available 14-30 Aug, no cryo connections either! | ||
** get OSP and go cold early Sep? | ** get OSP and go cold early Sep? |
Revision as of 14:27, 2 August 2010
Solenoid Coil Test Weekly Meeting
Location and Time
- Thu 29-Jul-2010 9:30am ARC 428
Agenda
- Vacations
- Test Lab power and cryo not available 14-30 Aug, no cryo connections either!
- get OSP and go cold early Sep?
- Test plan - Josh
- tags, HMI, etc.
- Telephone - Elliott
- Magnet power supply and interlock commissioning - Cody
- flow pressures and rates
- filters?
- interlock on strain gauges?
- Controls racks - Scot
- PLC programming/testing status - Mark W
- backup PLC programmer?
- UPS status - Mark W, Elliott
- relay modules, use in interlock system
- connection to PLC?
- EPICS <--> PLC communications - Wesley, Elliott
- connection to guard shack
- HMI and EWEB programming - Yi, Elliott
- Installation status - George, Mark S
- cryo can, platform and stand
- Two weeks notice to Errol - when?
- backup power in Test Lab?
- Coil repair status - George
- OSP documents and review - Elliott, George