* Aftermath of Director's Review - George, Mark, Jonathan, Elliott  
 
* Aftermath of Director's Review - George, Mark, Jonathan, Elliott  
 +
* Quench detection, fast/slow interlock chains for single coil test and full system - Elliott
 +
** need to schedule another meeting next week
 +
* UPS on power supply control system - Mark S
 
* PI Responsibilities during test - Jonathan
 
* PI Responsibilities during test - Jonathan
 
* OSP status - Elliott
 
* OSP status - Elliott

Revision as of 13:02, 27 October 2010

Solenoid Coil Test Weekly Meeting

Location and Time

  • Thu 28-Oct-2010 9:30 am ARC 428


Agenda

  • Aftermath of Director's Review - George, Mark, Jonathan, Elliott
  • Quench detection, fast/slow interlock chains for single coil test and full system - Elliott
    • need to schedule another meeting next week
  • UPS on power supply control system - Mark S
  • PI Responsibilities during test - Jonathan
  • OSP status - Elliott
  • Hall probe - Mark S
  • Installation and commissioning status - all
    • pressure testing and certifications
    • pumping/purging
    • connection to cryo system
    • ODH on platform?
    • what else?
  • Magnet power supply and interlock commissioning - Mark S
    • quench protection
    • shunt and ground fault detection
  • Controls racks - Scot
    • strain gauge and UPS interlocks
    • commissioning
    • anything else?
  • PLC programming/testing status - Mark W
    • UPS interlock
    • what's left?
  • EPICS - Hovanes
    • communication with Cryo Group
    • connection to guard shack and notification conditions
    • pager status and strategy
  • HMI and EWEB programming - Yi, Hovanes
    • current status
  • Coil repair status - George
  • Solenoid review 7-Dec
  • Purchase of another PLC and Ethernet module - Elliott
  • Hall D Technical web page
  • Preparations for testing next coil - George, Scot, Elliott
    • update P&I
    • splices
    • yoke location
    • piping adaptors
    • downstream yoke spacers
    • controls racks rewiring
    • connectors on next coil
    • what else?