'''Agenda''' | '''Agenda''' | ||
− | * Aftermath of Director's Review - George, Mark, Jonathan, Elliott | + | * [http://www.jlab.org/~wolin/DirReviewReport_Oct-2010.docx Aftermath] of Director's Review - George, Mark, Josh, Jonathan, Elliott |
− | * | + | ** redundancy in quench detection and other systems |
− | ** | + | ** redundant breaker in fast/slow interlock chains |
− | * UPS on power supply control system | + | ** high-speed DAQ for diagnosis of electrical problems |
+ | ** UPS on power supply control system | ||
+ | ** what needs to be done for the test vs for the experiment? | ||
* PI Responsibilities during test - Jonathan | * PI Responsibilities during test - Jonathan | ||
+ | ** Low power magnet testing 5A, 50A,100A - Elliott | ||
+ | ** High power magnet testing 100-1500A - Elliott | ||
+ | ** Identify possible turn to turn shorts during ramping - Eugene | ||
+ | ** Assess Heim column centering in coil - George | ||
+ | ** Assess Axial column forces - George | ||
+ | ** Estimate LN2 and He heat leak - Jonathan | ||
+ | ** Assess LN2 and LHe thermal siphons - Jonathan | ||
* OSP status - Elliott | * OSP status - Elliott | ||
* Hall probe - Mark S | * Hall probe - Mark S | ||
Line 21: | Line 30: | ||
** connection to cryo system | ** connection to cryo system | ||
** ODH on platform? | ** ODH on platform? | ||
+ | ** vacuum gate valve status | ||
** what else? | ** what else? | ||
* Magnet power supply and interlock commissioning - Mark S | * Magnet power supply and interlock commissioning - Mark S | ||
− | ** quench | + | ** quench protector wiring |
− | ** shunt | + | ** shunt |
+ | ** ground fault detection | ||
+ | ** should strain gauges be in interlock system? | ||
* Controls racks - Scot | * Controls racks - Scot | ||
** strain gauge and UPS interlocks | ** strain gauge and UPS interlocks | ||
** commissioning | ** commissioning | ||
+ | ** hook up redundant sensors | ||
** anything else? | ** anything else? | ||
* PLC programming/testing status - Mark W | * PLC programming/testing status - Mark W | ||
** UPS interlock | ** UPS interlock | ||
** what's left? | ** what's left? | ||
+ | ** another tutorial | ||
* EPICS - Hovanes | * EPICS - Hovanes | ||
** communication with Cryo Group | ** communication with Cryo Group | ||
Line 37: | Line 51: | ||
** [[pager_status_10_21_2010 | pager status ]] and strategy | ** [[pager_status_10_21_2010 | pager status ]] and strategy | ||
* HMI and [http://halldeweb1.jlab.org/user/web/plc_urls.html EWEB programming] - Yi, Hovanes | * HMI and [http://halldeweb1.jlab.org/user/web/plc_urls.html EWEB programming] - Yi, Hovanes | ||
− | ** | + | ** PID screens |
+ | ** program access to archived data | ||
+ | ** another tutorial | ||
* Coil repair status - George | * Coil repair status - George | ||
+ | * Learn how to use Linux for web and email - Elliott | ||
* Solenoid review 7-Dec | * Solenoid review 7-Dec | ||
* Purchase of another PLC and Ethernet module - Elliott | * Purchase of another PLC and Ethernet module - Elliott | ||
Line 49: | Line 66: | ||
** downstream yoke spacers | ** downstream yoke spacers | ||
** controls racks rewiring | ** controls racks rewiring | ||
+ | ** quench detector connections | ||
** connectors on next coil | ** connectors on next coil | ||
** what else? | ** what else? |
Latest revision as of 08:51, 28 October 2010
Solenoid Coil Test Weekly Meeting
Location and Time
- Thu 28-Oct-2010 9:30 am ARC 428
Agenda
- Aftermath of Director's Review - George, Mark, Josh, Jonathan, Elliott
- redundancy in quench detection and other systems
- redundant breaker in fast/slow interlock chains
- high-speed DAQ for diagnosis of electrical problems
- UPS on power supply control system
- what needs to be done for the test vs for the experiment?
- PI Responsibilities during test - Jonathan
- Low power magnet testing 5A, 50A,100A - Elliott
- High power magnet testing 100-1500A - Elliott
- Identify possible turn to turn shorts during ramping - Eugene
- Assess Heim column centering in coil - George
- Assess Axial column forces - George
- Estimate LN2 and He heat leak - Jonathan
- Assess LN2 and LHe thermal siphons - Jonathan
- OSP status - Elliott
- Hall probe - Mark S
- Installation and commissioning status - all
- pressure testing and certifications
- pumping/purging
- connection to cryo system
- ODH on platform?
- vacuum gate valve status
- what else?
- Magnet power supply and interlock commissioning - Mark S
- quench protector wiring
- shunt
- ground fault detection
- should strain gauges be in interlock system?
- Controls racks - Scot
- strain gauge and UPS interlocks
- commissioning
- hook up redundant sensors
- anything else?
- PLC programming/testing status - Mark W
- UPS interlock
- what's left?
- another tutorial
- EPICS - Hovanes
- communication with Cryo Group
- connection to guard shack and notification conditions
- pager status and strategy
- HMI and EWEB programming - Yi, Hovanes
- PID screens
- program access to archived data
- another tutorial
- Coil repair status - George
- Learn how to use Linux for web and email - Elliott
- Solenoid review 7-Dec
- Purchase of another PLC and Ethernet module - Elliott
- Hall D Technical web page
- Preparations for testing next coil - George, Scot, Elliott
- update P&I
- splices
- yoke location
- piping adaptors
- downstream yoke spacers
- controls racks rewiring
- quench detector connections
- connectors on next coil
- what else?