# Early procurement items for tagger microscope construction -- ''Richard'' | # Early procurement items for tagger microscope construction -- ''Richard'' | ||
# New diamond thinning proposal for SBIR Phase II with Sinmat -- Richard | # New diamond thinning proposal for SBIR Phase II with Sinmat -- Richard | ||
+ | # Updates on design of the Pair Spectrometer -- Sascha |
Revision as of 10:53, 4 April 2011
- Time: 11:00 EST
- Place: ESNET and EVO (with telephone bridge id 317 3697)
- Connecting: instructions are here
- Present:
Agenda
- Review recent beam tests in Hall B -- discussion
- online logbook for microscope prototype tests
- online logbook for active collimator tests
- summary of accomplishments
- experience with data acquisition, limiting factors
- experience with the trigger counters, limiting factors
- experience with the active collimator
- plans for data analysis
- prospects for further beam in Hall B, in case problems show up in the analysis
- Progress on tagger vacuum box design -- Tim
- Response so far on tagger magnet bid -- Tim
- Early procurement items for tagger microscope construction -- Richard
- New diamond thinning proposal for SBIR Phase II with Sinmat -- Richard
- Updates on design of the Pair Spectrometer -- Sascha