Difference between revisions of "May 5, 2011 SiPM Electrical and Cooling"

From GlueXWiki
Jump to: navigation, search
(Action Items from previous meetings)
(Tentative Agenda)
Line 14: Line 14:
 
# Schedule, reporting, and manpower (Elton)
 
# Schedule, reporting, and manpower (Elton)
 
# SiPM testing (Carl and Yi)
 
# SiPM testing (Carl and Yi)
#* Acceptance of First Article
+
# Mechanical (Jim)
# Mechanical cooling (Jim)
+
 
# Mechanical drawings (Chuck)
 
# Mechanical drawings (Chuck)
 +
# Geometry (Elton)
 
# Temperature compensation (Jack)
 
# Temperature compensation (Jack)
 
# Preamp-summing (Fernando)
 
# Preamp-summing (Fernando)
 
#* Will present a discussion of cabling and grounding next week.
 
#* Will present a discussion of cabling and grounding next week.
# Discussion of production testing
 
  
 
== Minutes ==
 
== Minutes ==
 
''Attending:
 
''Attending:

Revision as of 17:21, 4 May 2011

References

Action Items from previous meetings

  1. Check impact of material at low end of readout, both in the tubes for cooling fluid but also in the Cu cooling plate. Need to check effect on particle trajectories.
    • Suggested mods to mechanical: make SiPM holder one piece (instead of 4), increase thickness of holder to 3/8", increase size of thermal plate to cover all amplifiers.

Tentative Agenda

  1. Announcements
  2. Action Items
  3. Schedule, reporting, and manpower (Elton)
  4. SiPM testing (Carl and Yi)
  5. Mechanical (Jim)
  6. Mechanical drawings (Chuck)
  7. Geometry (Elton)
  8. Temperature compensation (Jack)
  9. Preamp-summing (Fernando)
    • Will present a discussion of cabling and grounding next week.

Minutes

Attending: