# Cables need to be ordered for the SiPM production test setup (Chris) | # Cables need to be ordered for the SiPM production test setup (Chris) | ||
# Values of trim resistors for nominal operation to Chris (Jack). Chris to add them to the BOM. | # Values of trim resistors for nominal operation to Chris (Jack). Chris to add them to the BOM. | ||
+ | # Order any missing mechanical parts for assembly of mini-Bcal (Jim) | ||
== Tentative Agenda == | == Tentative Agenda == |
Revision as of 19:15, 5 January 2012
Action Items from previous meetings
- U-boards need to be ordered for the mini-Bcal (Chris)
- Cables need to be ordered for the SiPM production test setup (Chris)
- Values of trim resistors for nominal operation to Chris (Jack). Chris to add them to the BOM.
- Order any missing mechanical parts for assembly of mini-Bcal (Jim)
Tentative Agenda
- Announcements
- Action Items
- Schedule, reporting, and manpower (Elton)
- SiPM production testing (everyone)
- Mechanical assembly (Scot)
- Mechanical (Jim)
- Mechanical drawings (Chuck)
- Temperature compensation (Jack)
- Preamp-summing (Fernando/Chris)
- SiPM testing (Ivan)
Minutes
Attending: