Difference between revisions of "Mar 29, 2011 SiPM Electrical and Cooling"
From GlueXWiki
(→Action Items from previous meetings) |
(→Action Items from previous meetings) |
||
Line 4: | Line 4: | ||
# Develop front and back views of jumper sheets. Also get latest version of drawings (Jack) | # Develop front and back views of jumper sheets. Also get latest version of drawings (Jack) | ||
# Request Hamamatsu data sheets from Chile to be used as input to jumper settings for boards (Elton) | # Request Hamamatsu data sheets from Chile to be used as input to jumper settings for boards (Elton) | ||
+ | # Double-check that the jumper settings for #37 (U-board counting) are correct (Jack) | ||
== Tentative Agenda == | == Tentative Agenda == |
Revision as of 17:07, 22 March 2012
Action Items from previous meetings
- Determine if swapped bias pins was accidental or in design (Chris)
- Develop front and back views of jumper sheets. Also get latest version of drawings (Jack)
- Request Hamamatsu data sheets from Chile to be used as input to jumper settings for boards (Elton)
- Double-check that the jumper settings for #37 (U-board counting) are correct (Jack)
Tentative Agenda
- Announcements
- Action Items
- Schedule, reporting, and manpower (Elton)
- SiPM production testing (everyone)
- Mechanical assembly (Scot)
- Mechanical (Jim)
- Mechanical drawings (Chuck)
- Temperature compensation (Jack)
- Preamp-summing (Chris)
Minutes
Attending: