Difference between revisions of "GlueX TOF Meeting, September 27, 2012"
(notes as minutes) |
|||
Line 25: | Line 25: | ||
Talks can be deposited in the directory <code>/group/halld/www/halldweb1/html/talks/2012-3Q</code> on the JLab CUE. This directory is accessible from the web at https://halldweb1.jlab.org/talks/2012-3Q/ . | Talks can be deposited in the directory <code>/group/halld/www/halldweb1/html/talks/2012-3Q</code> on the JLab CUE. This directory is accessible from the web at https://halldweb1.jlab.org/talks/2012-3Q/ . | ||
+ | |||
+ | =Minutes= | ||
+ | |||
+ | tof meeting notes, Sep. 27 | ||
+ | |||
+ | sasha, paul | ||
+ | elton, beni, tim, chuck, mark | ||
+ | |||
+ | |||
+ | |||
+ | mini-tof | ||
+ | material coming in | ||
+ | big steel channel, getting it from down the road from jlab | ||
+ | have to buy 20 ft length piece | ||
+ | mini0tof: issue | ||
+ | |||
+ | gluing jig, materials arriving | ||
+ | |||
+ | procurements, moving forward | ||
+ | specifications to eljen and stgobain, heard back from eljen | ||
+ | AJ200 revamped machines, can get scintillator sooner than anticipated, within 6 weeks of order | ||
+ | flook of orders to both firms for scintillator, japanese reactor crisis-related | ||
+ | chuck halbert | ||
+ | |||
+ | uvt acrylics, addtional quotes requested, another company can provide same material, came in better | ||
+ | 240 ft can be delivered in 6 weeks | ||
+ | purchased 2 rods from new company | ||
+ | 3m, esr daylighting film | ||
+ | trying for long rolls, rather than small sheets | ||
+ | |||
+ | laser scattering | ||
+ | |||
+ | construction jigs, increased spacing | ||
+ | glue 9 scintillators at a time | ||
+ | ian working on a wrapping jig | ||
+ | u- channel, with wrapping material coming up and wrap material around | ||
+ | rtv for mounting pmt's spin-off of ge sillicon, momentum produces rtv 615 and 655, 615 used at other experiments, | ||
+ | |||
+ | tests done with glue, done on a verticall surface, looks good | ||
+ | 20 ft-lb torque, no budge | ||
+ | |||
+ | halld engineering release documents, copy it, change it ,change specificiation for the tof to drop dimentions |
Revision as of 10:40, 28 September 2012
GlueX TOF Meeting
Thursday, September 27, 2012
10:00 am EDT
JLab: CEBAF Center, F326
Agenda
- Announcements
- Review of last TOF bi-weekly meeting
- Mechanical design
- Contract status -> EVMS status
- Calibration and Alignment
- Technical Design Report contribution
Communication
Videoconference
- ESNet: 8542553
- EVO: EVO site
- meeting link
- Phone bridge ID: 13 7104
Slides
Talks can be deposited in the directory /group/halld/www/halldweb1/html/talks/2012-3Q
on the JLab CUE. This directory is accessible from the web at https://halldweb1.jlab.org/talks/2012-3Q/ .
Minutes
tof meeting notes, Sep. 27
sasha, paul elton, beni, tim, chuck, mark
mini-tof material coming in big steel channel, getting it from down the road from jlab have to buy 20 ft length piece mini0tof: issue
gluing jig, materials arriving
procurements, moving forward specifications to eljen and stgobain, heard back from eljen AJ200 revamped machines, can get scintillator sooner than anticipated, within 6 weeks of order flook of orders to both firms for scintillator, japanese reactor crisis-related chuck halbert
uvt acrylics, addtional quotes requested, another company can provide same material, came in better 240 ft can be delivered in 6 weeks purchased 2 rods from new company 3m, esr daylighting film trying for long rolls, rather than small sheets
laser scattering
construction jigs, increased spacing glue 9 scintillators at a time ian working on a wrapping jig u- channel, with wrapping material coming up and wrap material around rtv for mounting pmt's spin-off of ge sillicon, momentum produces rtv 615 and 655, 615 used at other experiments,
tests done with glue, done on a verticall surface, looks good 20 ft-lb torque, no budge
halld engineering release documents, copy it, change it ,change specificiation for the tof to drop dimentions