(Created page with "__TOC__ == Meeting Time and Place == Friday, September 13, 2013 at 1:30 PM At Jefferson Lab, the meeting will be held in F326 == Connections == To connect from the outside, pl...") |
(→Agenda) |
||
Line 29: | Line 29: | ||
# Magnet Status | # Magnet Status | ||
#* Impact of Magnet work on installation. | #* Impact of Magnet work on installation. | ||
− | # Updates to the Mechanical Installation Schedule ([[Media: | + | # Updates to the Mechanical Installation Schedule ([[Media:Sept 2013 Install Schedule.pdf | Sept Rendition of Install Schedule]]) (Tim) |
# Electronics Installation Schedule (Fernando) [[https://halldweb1.jlab.org/wiki/index.php/Status_%26_Schedules | Schedule]] | # Electronics Installation Schedule (Fernando) [[https://halldweb1.jlab.org/wiki/index.php/Status_%26_Schedules | Schedule]] | ||
# Installation Updates (<b>Not a construction report</b>) | # Installation Updates (<b>Not a construction report</b>) |
Revision as of 15:30, 12 September 2013
Contents
Meeting Time and Place
Friday, September 13, 2013 at 1:30 PM At Jefferson Lab, the meeting will be held in F326
Connections
To connect from the outside, please use ESNET
- ) ESNET: 8542553
- )To connect by telephone (supported on request only) dial:
- You can look up toll-free number at http://www.readytalk.com/intl
- US and Canada: (866)740-1260 (toll free)
- International: (303)248-0285 (toll call)
- enter access code followed by the # sign: 3421244#
Desktop Sharing
You can view the computer desktop in the meeting room at JLab via the web.
- Go to http://esnet.readytalk.com
- In the "join a meeting" box enter the Hall D code: 3421244
- Fill in the participant registration form.
Up to GlueX/Hall-D Installation Meetings
Action Items From Last Meeting
Agenda
- Announcements
- Magnet Status
- Impact of Magnet work on installation.
- Updates to the Mechanical Installation Schedule ( Sept Rendition of Install Schedule) (Tim)
- Electronics Installation Schedule (Fernando) [| Schedule]
- Installation Updates (Not a construction report)
- Counting House Infracstructure
- Trigger and DAQ Installation
- Slow Control Installation
- Tagger Magnet Installation
- BCAL Installation
- FCAL Installation
- FDC Installation
- CDC Installation
- TOF Installation
- Start Counter Installation
- Microscope Installation
- Tagger Array Installation
- Pair Spectrometer Installation