Difference between revisions of "September 13, 2013 Installation"
From GlueXWiki
(→Agenda) |
(→Agenda) |
||
Line 37: | Line 37: | ||
#* Tagger Magnet Installation | #* Tagger Magnet Installation | ||
#* BCAL Installation [http://gluex.phys.uregina.ca/content/photo/downstream-view-bcal-after-installation Downstream View], [http://gluex.phys.uregina.ca/content/photo/upstream-view-bcal-after-installation Upstream View], [http://gluex.phys.uregina.ca/content/photo/closeup-upstream-view-bcal-after-installation-four-support-strips-are-visible Closeup Upstream View] | #* BCAL Installation [http://gluex.phys.uregina.ca/content/photo/downstream-view-bcal-after-installation Downstream View], [http://gluex.phys.uregina.ca/content/photo/upstream-view-bcal-after-installation Upstream View], [http://gluex.phys.uregina.ca/content/photo/closeup-upstream-view-bcal-after-installation-four-support-strips-are-visible Closeup Upstream View] | ||
+ | #** [https://halldweb1.jlab.org/talks/2013-3Q/bcal_photos/ more photos] | ||
#* FCAL Installation | #* FCAL Installation | ||
#* FDC Installation | #* FDC Installation |
Revision as of 12:33, 13 September 2013
Contents
Meeting Time and Place
Friday, September 13, 2013 at 1:30 PM At Jefferson Lab, the meeting will be held in F326
Connections
To connect from the outside, please use ESNET
- ) ESNET: 8542553
- )To connect by telephone (supported on request only) dial:
- You can look up toll-free number at http://www.readytalk.com/intl
- US and Canada: (866)740-1260 (toll free)
- International: (303)248-0285 (toll call)
- enter access code followed by the # sign: 3421244#
Desktop Sharing
You can view the computer desktop in the meeting room at JLab via the web.
- Go to http://esnet.readytalk.com
- In the "join a meeting" box enter the Hall D code: 3421244
- Fill in the participant registration form.
Up to GlueX/Hall-D Installation Meetings
Action Items From Last Meeting
Agenda
- Announcements
- Magnet Status
- Impact of Magnet work on installation.
- Updates to the Mechanical Installation Schedule ( Sept Rendition of Install Schedule) (Tim)
- Electronics Installation Schedule (Fernando) [| Schedule]
- Installation Updates (Not a construction report)
- Counting House Infracstructure
- Trigger and DAQ Installation
- Slow Control Installation
- Tagger Magnet Installation
- BCAL Installation Downstream View, Upstream View, Closeup Upstream View
- FCAL Installation
- FDC Installation
- CDC Installation
- TOF Installation
- Start Counter Installation
- Microscope Installation
- Tagger Array Installation
- Pair Spectrometer Installation
- A.O.B.