Difference between revisions of "CDC travel plans"
From GlueXWiki
Line 6: | Line 6: | ||
##Arrival after ? pm - go to Hall D, drive in, CDC in truck overnight, drive to EEL the next day and unload | ##Arrival after ? pm - go to Hall D, drive in, CDC in truck overnight, drive to EEL the next day and unload | ||
+ | After arrival at JLab (longer term plans) | ||
+ | #CDC is to be stored in EEL 126? until FDC installation is complete | ||
+ | #HV blocks need to be added | ||
+ | #CDC mini-readout in EEL can be set up once FDC has moved into Hall D | ||
+ | #Expect CDC installation to be in Jan 2014 (engineering) or Dec 2013 (electronics) [[September_27,_2013_Installation | schedules are linked to installation meeting Sept 27]] | ||
Preparations: | Preparations: | ||
Line 26: | Line 31: | ||
#Arrange time with fork lift driver - Gary | #Arrange time with fork lift driver - Gary | ||
− | + | ||
− | + | ||
− | + | ||
− | + | ||
− | + | ||
Revision as of 10:57, 8 October 2013
Overview
- Load up at CMU - looking at Oct 28-30 or Nov 4-6
- Ideally, store truck indoors overnight
- Drive to JLab
- Arrival before ?pm - go to EEL to unload
- Arrival after ? pm - go to Hall D, drive in, CDC in truck overnight, drive to EEL the next day and unload
After arrival at JLab (longer term plans)
- CDC is to be stored in EEL 126? until FDC installation is complete
- HV blocks need to be added
- CDC mini-readout in EEL can be set up once FDC has moved into Hall D
- Expect CDC installation to be in Jan 2014 (engineering) or Dec 2013 (electronics) schedules are linked to installation meeting Sept 27
Preparations:
- Add reinforcements to CDC cart for forklift
- Order materials for reinforcements
- Calculate position of CDC's CM
- Swap straight wheels for swivel wheels
- Order swivel wheels
- Find filters to cap CDC gas tubes
- Wrap CDC in bubblewrap
- Order bubble-wrap
- Cut dual-density foam to size
- Locate mooring snubbers
- Rent a truck
- Need to measure temp near CDC - buy long thermocouple?
- Update packing list - extra things to bring (HVBs, manifold etc) installation doc with packing list
- Book accommodation at resfac
- Find somewhere to keep truck indoors overnight at CMU - Naomi
- Negotiate loading bay access - Curtis
- Arrange time with fork lift driver - Gary
Equipment for readout
- 4 long scint paddles are to travel down from CMU
- Do we need to bring any NIM modules?
Shopping list
- Unistrut & fittings to modify cart
- Swivel wheels
- Bubble wrap
- Truck
- Thermocouple?
- Do we need to borrow a mini-compressor for the cart tires?