(Created page with "=== Organization === * Time: 11:30 EDT * Place: For those at JLab the meeting will be held in F326 and in the Hall D counting house. * Connecting: detailed instructions are [[Tag...") |
(→Agenda) |
||
Line 11: | Line 11: | ||
=== Agenda === | === Agenda === | ||
# Announcements | # Announcements | ||
− | # [[Run Coordination Meetings| | + | # [[Run Coordination Meetings|Review of accomplishments during first ~4 days of beam]] - ''Alexandre D.'' |
# [https://logbooks.jlab.org/entry/3301685 Rates seen in Hall D collimator cave profile monitor] - ''Alexandre D.'' | # [https://logbooks.jlab.org/entry/3301685 Rates seen in Hall D collimator cave profile monitor] - ''Alexandre D.'' | ||
− | # | + | # What must be accomplished before commissioning can restart |
− | # | + | #* evaluation of tagger hall backgrounds, esp. neutrons - ''discussion'' |
− | # | + | #* installation of electronics crates in tagger hall - ''Nick'', ''Alex'', ''others?'' |
+ | #* reinstallation and checkout of TAGM readout electronics - ''Alex'', ''Brendan'' | ||
+ | #* elevation of TAGM counters to the focal plane height - ''Tim'' | ||
+ | #* reinstallation and checkout of TAGH downstream counters - ''Nathan'', ''Natalie'' | ||
+ | #* analysis of scans with active collimator, initial calibration - ''Richard'' | ||
+ | #* anything in Hall D? - ''Alexandre'' | ||
+ | # Goals for the next two weeks | ||
+ | # Immediate questions for simulation? | ||
# ''any other business'' | # ''any other business'' |
Revision as of 11:21, 10 November 2014
Organization
- Time: 11:30 EDT
- Place: For those at JLab the meeting will be held in F326 and in the Hall D counting house.
- Connecting: detailed instructions are here
- H.323 ip address: 199.48.152.152
- web browser: https://bluejeans.com/536076821
- phone: 408-740-7256 or 888-240-2560
- Conference id: 536076821
- Present:
Agenda
- Announcements
- Review of accomplishments during first ~4 days of beam - Alexandre D.
- Rates seen in Hall D collimator cave profile monitor - Alexandre D.
- What must be accomplished before commissioning can restart
- evaluation of tagger hall backgrounds, esp. neutrons - discussion
- installation of electronics crates in tagger hall - Nick, Alex, others?
- reinstallation and checkout of TAGM readout electronics - Alex, Brendan
- elevation of TAGM counters to the focal plane height - Tim
- reinstallation and checkout of TAGH downstream counters - Nathan, Natalie
- analysis of scans with active collimator, initial calibration - Richard
- anything in Hall D? - Alexandre
- Goals for the next two weeks
- Immediate questions for simulation?
- any other business