- Trigger Commissioning Plan
- Integrate PS trigger to the global DAQ (1 - 2 days)
- Tune trigger parameters (trigger threshold scans, tune timing offsets) and study performance for
- - FCAL (2 days)
- Performed threshold scans for noise/cosmic runs [Log entry]
- - BCAL (1 day)
- - FCAL & BCAL (1 day)
- - ST and TOF (1 day)
- - Coincidence of FCAL/BCAL and ST/TOF (2 days)
- - Multiple triggers in the system (2-3 days)
- Trigger hit-pattern is written to the trigger record
- - FCAL (2 days)
- Trigger Monitoring
- - Use config files to initialize electronics modules